Infrastructure
Wuhan's new landmark achieves a 36 meter high pillarless hall
Seetao 2025-04-02 09:20
  • The first domestically developed 'weakly correlated' suspended steel structure has been completed
Reading this article requires
5 Minute

On April 1st, the Wuhan Wuchang District Government Center project, undertaken by China Railway 18th Bureau, passed joint acceptance, marking the completion of the first "weakly correlated" steel structure suspension system project in China. This project innovatively adopts the technology of roof bridge direct connection steel tie rod, creating a super large column free space with a projected area of 900 square meters and a height of 36 meters on floors 9-16. Its 641 square meter single cantilever area sets a record for the largest scale of similar buildings.

During construction, the project team utilized BIM technology for precise modeling and adopted the "overall lifting+reverse assembly" process. Eight hydraulic lifters were used to simultaneously lift 380 tons of steel structure (equivalent to the weight of eight C919 passenger planes), completing the main construction in just 2 days per floor, which is three times more efficient than traditional construction methods. This technological breakthrough creates a transparent visual effect of "lake light entering the room" inside the building, while reducing the amount of steel used in the structure by 30%.

As a new landmark in Wuchang District, this 141300 square meter government complex integrates green ecological concepts, and its "weak correlation" suspension system provides a new paradigm for large-span space design of high-rise buildings in China. After the project is put into operation, the government service functions of 26 departments will be centrally integrated, and it is expected to receive more than 5000 people per day, becoming a demonstration window for optimizing the business environment in Wuhan. (This article is from the official website of Jian Dao www.seetao.com. Reproduction without permission is prohibited, otherwise it will be prosecuted. Please indicate Jian Dao website+original link when reprinting.) Jian Dao website strategy column editor/Wu Juan

Comment

Related articles

Transportation

Tongyong High speed Railway launches full track laying

10-17

Transportation

The renovation of Linha Railway has entered the stage of electrification construction

10-16

Transportation

Entering the key tunnel of the Yia Railway

10-16

Transportation

Hanoi Inks Contract for Five Metro Lines, Chinese Rail Firms Eye New Opportunities

10-16

Transportation

Guinea President Rides Maiden Passenger Train of Trans Guinea Railway

10-16

Transportation

Badain Jaran Desert Energy Base Supporting Railway Public Announcement Winning Bid

10-16

Collect
Comment
Share

Retrieve password

Get verification code
Sure