In order to achieve carbon emission reduction targets, the development of new energy industries in various regions has accelerated. Recently, the People's Government of Inner Mongolia Autonomous Region issued the "14th Five-Year Plan for Energy Development of Inner Mongolia Autonomous Region".
Development Goals
- Energy security guarantee. Maintain steady growth in energy supply, with a comprehensive energy production capacity of 820 million tons of standard coal, of which coal output is stable at around 1.05 billion tons, and installed power generation capacity reaches 271 million kilowatts.
——Optimization of energy structure. Coal consumption will achieve zero growth, the proportion of consumption will be reduced to less than 75%, the proportion of non-fossil energy consumption will reach 18%, and the proportion of new energy installed capacity will exceed 50%. Renewable energy consumption accounted for 35%. Newly added non-fossil energy installed capacity accounted for more than 60% of all new installed capacity.
- Improved energy efficiency. The energy consumption intensity will be reduced by more than 15% compared with that in 2020, and the carbon dioxide emission intensity will not be lower than the national target requirements. The coal consumption of coal-fired power units has dropped to less than 305 grams of standard coal per kWh, and the proportion of flexible power supply has exceeded 11%.
——Energy innovation and change. The investment intensity of energy research and development has been doubled, and the application of major key technologies such as hydrogen energy, large-scale energy storage, and carbon capture and storage has taken the lead in making breakthroughs.
——Energy services for the benefit of the people. The per capita electricity consumption of urban and rural residents has increased to more than 900 kWh, the pipeline natural gas has covered more than 66% of the flags (counties and districts), and the clean heating coverage has exceeded 80%. The general energy service level represented by "access to electricity" has been significantly improved.
Expand the wind-solar hydrogen storage industry and cultivate new growth poles of modern energy
Efforts will be made to build a wind energy industry cluster. By 2025, localized production of key components such as main bearings, gearboxes, generators, and blade materials will be achieved. The manufacturing capacity of complete fans will reach 5,500 sets, which can meet more than 80% of local construction needs. The scale of the fan manufacturing industry will reach 1,000. billion.
Strive to build a photovoltaic industry cluster. By 2025, the production scale of crystalline silicon materials will account for more than 40% of the national total, the production capacity of solar cell modules will reach 3 million kilowatts, which can meet more than 80% of local construction needs, and the overall industrial scale of photovoltaic manufacturing will reach 100 billion yuan.
Support the cultivation of hydrogen energy industry clusters. By 2025, the key core components of hydrogen energy will be produced locally, and the total output value of the hydrogen energy industry will strive to reach 100 billion yuan.
Support the cultivation of energy storage industry clusters. By 2025, the production scale of energy storage equipment will reach 10 million kWh, and the core components of energy storage will be fully produced on-site, forming an energy storage manufacturing industry cluster with an output value of 100 billion yuan.
Wind-solar hydrogen storage industry cluster
Wind energy industry cluster: focus on building Baotou Rare Earth High-tech Zone, Baotou Guyang and Damao Banner, Tongliao High-end Equipment Manufacturing Industrial Park, Ulanqab Modern Energy Innovation Demonstration Park, Ulanqab Zero-Carbon Industrial Park, Ordos Zero-Carbon Industrial Park , Bayannaoer Economic and Technological Development Zone and other wind power key components manufacturing and complete machine manufacturing base.
Photovoltaic industry cluster: focus on the construction of crystalline silicon material production bases such as Baotou Kun District and Tuyou Banner, Hohhot Solar Energy Industrial Park, and photovoltaic equipment manufacturing projects such as Ordos.
Hydrogen energy industry cluster: focus on building Hohhot hydrogen energy technology research and development base, Baotou hydrogen metallurgy, hydrogen industry chain and fuel cell vehicle research and development and manufacturing base, Ulanqab and Ordos hydrogen energy industrial park, Wuhai hydrogen fuel engine hydrogen energy equipment manufacturing, etc.
Energy storage industry cluster: focus on building energy storage and power battery equipment manufacturing projects in Baotou, Ulanqab, Ordos, Wuhai, etc.
Implement the new energy multiplication project and build a new modern energy center
By 2025, take the lead in building an energy supply system with new energy as the mainstay in the country. The installed capacity of new energy will reach more than 135 million kilowatts, and the installed capacity of new energy will account for more than 50%, and the annual emission reduction of carbon dioxide will be about 200 million tons. Contribute to the achievement of carbon peaking.
Promote the construction of new energy bases. Coordinate new energy development and grassland ecological protection, strictly abide by the "three districts and three lines" of the autonomous region, and in principle no new wind power and photovoltaic projects will be built in nature reserves, ecologically fragile areas, and ecologically functional areas.
Focus on building 10,000-kilowatt-level wind power bases in Baotou, Ulanqab, Ordos, Bayannaoer, Alxa League, and Tongliao in eastern Inner Mongolia, and promote concentrated and contiguous development of wind power along the border. million kilowatts of wind power projects.
New energy multiplication project
Large-scale wind power base in Jiziwan of the Yellow River: Make full use of the abundant wind energy resources in the Jiziwan area of the Yellow River, and plan and construct in the borders and desert areas of Hubao'e, Ulanqab, Bayannaoer, Alxa League and other alliance cities Large wind power base.
Photovoltaic ecological governance: Fully considering factors such as system access and ecological protection, plan and build photovoltaic sand control bases in Kubuqi Desert, Ulan Buhe Desert, Tengger Desert and other regions, and dump soil in coal mining subsidence areas and open-pit mines. Construction of photovoltaic ecological management projects in mining areas.
New energy delivery bases: add a number of new energy bases in the existing UHV delivery channels from Mengxi to Tianjin South and Shanghai Temple to Shandong; actively promote the construction of delivery channels from Mengxi to North China and East China, and promote new Construction of energy bases to achieve a high proportion of renewable energy delivery.
Distributed projects: Promoting the construction of a number of distributed wind power and distributed photovoltaic projects in the region according to local conditions.
Flexible grid engineering
Power supply flexibility improvement: priority is given to promoting the thermal power flexibility transformation in Hubaoe, Tongliao and other regions, and the whole region strives to complete the thermal power flexibility transformation scale of about 30 million kilowatts.
Pumped storage power station: Accelerate the construction of Chifeng Zhirui pumped storage power station, and advance the preliminary work of Baotou Meidai, Hulunbeier Yakeshi, Xinggan League Solon, Ulanqabfeng Town, Wuhai and other pumped storage power stations.
Optimizing the power grid structure: The Mengxi Power Grid has added more than 30,000 kilometers of new lines, and newly added main transformers of more than 90 million kVA, focusing on the construction of Ninger-Jubaozhuang, Gandir-Chuanzhang, Hetao-Xiangtai-Qianli Mountain and other power transmission and transformation strengthening projects. East Mongolia Power Grid has added more than 30,000 kilometers of new lines, and newly added main transformers of more than 35 million kVA, focusing on the construction of Bahrain-Jinsha-Fuxin (Inner Mongolia section), Pingchuan, Dongshan, Ningcheng, Zhurihe, and Aldu-Pingchuan and other power transmission projects.
Intelligent construction of power grid: promote intelligent transformation of Tongliao Naiman 500 kV Substation, Manzhouli 500 kV Substation, Xiangde (Ulan Buhe) 220 kV Substation, Ulanqab Dongyu 220 kV Substation, etc. level of intelligence.
Establish a flexible adjustment mechanism: improve the intelligence level of the power dispatching system, and improve the dispatching level of the large power grid; improve the market-based allocation mechanism for factors such as power spot, power capacity, and auxiliary services, and improve the power demand-side response capability.
Incremental distribution network construction: Continue to promote the construction of incremental distribution network demonstration projects that have been included in the pilot program, such as the Dalat Economic Development Zone in Ordos City. Editor / Xu Shengpeng