Seetao 2023-06-14 09:06
  • The construction scale of this project is 1.2 million kilowatts, with a total investment of 9.6 billion yuan
  • The initial installation capacity of the power station is four 300MW single stage mixed flow reversible water pump turbine units, with a total construction period of 72 months
Reading this article requires
6 Minute

On June 12, 2023, the reporter from Dao.com learned from the website of Bayannur Municipal People's Government that the results of the competitive negotiation on investment invitation of the investors of the Taiyanggou Pumped-storage hydroelectricity Project in Urad Rear Banner have been publicized.

The main investor of Urad Rear Banner Taiyanggou Pumped-storage hydroelectricity Project is a consortium led by Inner Mongolia Power Group Comprehensive Energy Co., Ltd. and formed with Inner Mongolia Energy Power Generation Investment Group New Energy Co., Ltd. and Power Construction Corporation of China Group Beijing Survey, Design and Research Institute Co., Ltd.

The power station is located in Bayinbaolige Town, Urad Rear Banner, Bayannur City. The project is about 60km away from Bayannur. It is a daily regulation Pumped-storage hydroelectricity. The pivotal project is mainly composed of upper reservoir, water conveyance system, underground powerhouse system, lower reservoir, ground switch station and other buildings. The project construction scale is 1.2 million kW Pumped-storage hydroelectricity and supporting facilities. The preliminary installed capacity is 4 300MW single-stage mixed flow reversible pump turbine units, The rated head of the power station is 389m, and the normal storage levels of the upper and lower reservoirs are 1616 and 1210m, respectively. The total construction period is 72 months, and the total investment is 9.6 billion yuan. After the completion of the power station, it mainly undertakes tasks such as peak shaving, frequency regulation, energy storage, system backup, and black start of the Inner Mongolia power grid.

As the first Pumped-storage hydroelectricity in Bayannaoer region, the project is of great significance to ensure the safe and stable economic operation of the power system in Bayannaoer region, increase the consumption of new energy power, promote the adjustment of energy structure, and achieve sustainable development. It is also of great significance to thoroughly implement the autonomous region's strategic objectives of "two firsts and two surpasses", help "carbon peak and carbon neutrality", and promote the construction of ecological civilization, Promoting the low-carbon transformation of the company's energy, ensuring energy security and supply, and promoting high-quality economic and social development is of great practical significance. Editor/Zhao E


Comment

Related articles

Hydropower

Dashixia Hydropower Station sprints for first investment in June

04-23

Hydropower

Restart bidding after 85% completion Romania's 55MW hydropower station enters final sprint

04-06

Hydropower

China's hydropower technology innovation welcomes a new platform

04-05

Hydropower

Romania's hydropower expansion sprint: Nehoia ș u 2 project launches bidding

04-04

Hydropower

Itomubiara Hydropower Station launches automation upgrade and renovation

04-03

Hydropower

The key section of Yunnan 39.7 billion GS hydropower station has been finalized

03-25

Collect
Comment
Share

Retrieve password

Get verification code
Sure