Taipingling Nuclear Power Plant Unit 2 was successfully installed
Seetao 2024-05-29 16:57
  • The installation of generator stator provides a strong guarantee for the construction progress of the whole nuclear power project
Reading this article requires
6 Minute

On May 20, 2024, the stator of the main generator of Unit 2 of Huizhou Nuclear Power Plant was accurately and smoothly lifted onto the generator platform. The achievement of this important milestone not only symbolizes the official start of the installation of the generator body, but also lays a solid foundation for the full-scale installation of the conventional island of Unit 2.

Weighing more than 400 tons of generator stator, its huge size, 13 meters long, 6 meters wide, 5 meters high, is an indispensable heavyweight equipment in Huizhou nuclear power project. Its manufacturing quality and production schedule are directly related to the smooth progress of the whole project. The generator team of Huizhou Nuclear Power Plant was involved in the installation preparation work early, and on the basis of learning the installation experience of the No. 1 generator, they carried out more strict and fine control over the installation quality and safety of the No. 2 unit, so as to achieve a higher improvement.

From the moment the generator stator is shipped, Huizhou Nuclear Power attaches great importance to every link in its transportation process. They arranged for professional personnel to regularly track the progress of the stator transportation and record the maintenance during transportation in detail to ensure that the generator stator was fully protected during transportation. This meticulous management measures ensure that the quality of equipment in all aspects of design, manufacturing, transportation and installation is strictly guaranteed.

At the critical moment of 2024, which is defined by the company as a decisive year of practical work, the successful placement of the generator stator of Taiping Ling Nuclear Power Unit 2 undoubtedly marks another important milestone in the construction of the nuclear power project. This achievement not only shows the superb technical strength and exquisite operation level of the project team, but also lays a solid foundation for the subsequent installation and commissioning work.

The weight and size of the generator stator are quite large, and its successful lifting and placement is a full reflection of the technical strength and safety management of the project team. At the same time, this also provides a strong guarantee for the construction progress of the entire nuclear power project, helping to ensure that the project is carried out smoothly according to the established schedule.Editor/Zhang Liyuan

Comment

Related articles

Nuclear power

China has approved the construction of five nuclear power plants at a time

05-26

Nuclear power

14.5 billion yuan to build! China's largest nuclear fusion project

05-13

Nuclear power

Uzbekistan plans to build a large nuclears power plant by 2040

10-14

Nuclear power

Uzbekistan plans to build a large nuclear power plant by 2040

10-14

Nuclear power

Fujian Zhangzhou Nuclear Power Unit 4 Nuclear Island officially starts construction

09-27

Nuclear power

The reactor vessel of Unit 8 of Tianwan Nuclear Power Plant was successfully lifted

09-06

Collect
Comment
Share

Retrieve password

Get verification code
Sure