Recently, the Heilongjiang Provincial Highway Construction Bureau announced the list of winning bids for Ji-Hei Expressway. The project is divided into A1-A14 and B1-B6 bid sections, a total of 20 bid sections.
China Railway Construction Bridge Bureau won the bid for section A1 with 390 million yuan; China Communications First Navigation Bureau won the bid for section A2 with 170 million yuan; Longjian Road and Bridge No. 2 Company of Heilongjiang Province won the bid for section A3 with 450 million yuan; Longjian Road and Bridge won the bid for 170 million yuan Won the bid for A4 section; Guizhou Road and Bridge with 400 million yuan for A5 section; Heilongjiang Longjian Road and Bridge No. 4 Company with 560 million yuan for A6 and A7 sections; Heilongjiang Nongken Jiangong Road and Bridge won the bid for A8 section with 230 million yuan; China Railway 11th Bureau The second company won the bid for section A9 with 480 million yuan; Longjian Road and Bridge won the bid for section A10 with 250 million yuan; Zhengping Road and Bridge won the bid for section A11 with 440 million yuan; Longjian Road and Bridge No. 2 Company of Heilongjiang Province won the bid for section A12 with 230 million yuan; The No. 4 Company of Jiaotong Second Public Bureau won the bid of A13 for 520 million yuan; Sichuan Road and Bridge won the A14 bid for 350 million.
The first company of China Communications Construction Company won the B1 bid for 310 million yuan; Longjian Road and Bridge No. 1 Company of Heilongjiang Province won the B2 bid for 280 million yuan; Longjian Road and Bridge No. 5 Company of Heilongjiang Province won the B3 bid for 330 million yuan; Heilongjiang Dragon Jianluqiao No. 1 Company won the B4 bid for 390 million yuan; Sichuan Ruitong won the B5 bid for 270 million yuan; China Railway First Bureau won the B6 bid for 400 million yuan.

The main line of the project is 151.631 kilometers long. A total of 1 extra-large bridge, 6 bridges, 11 medium bridges, 8 small bridges and 231 culverts have been set up. 11 interchanges. There are 3 service areas, 2 parking areas, and 8 ramp toll stations. There are 34 separation bridges on the main line, 30 under the separation bridge, 24 overpasses, 12 passage bridges, 65 passage box culverts, and 7 pipeline crossings. The design speed is 120 kilometers per hour, and the four-lane highway standard is adopted.
The Harbin Ring Expressway is 31.653 kilometers long, with 1 small bridge and 36 culverts; 3 interchanges, 1 service area, 2 ramp toll stations, 5 main lines of the separation bridge, and the main line of the separation bridge There are 13 underpasses, 4 vehicle flyovers, 3 passage bridges, 12 passage culverts, and 2 pipeline crossings.
The construction of the section from Shanhe to Harbin will bring closer ties between the two provinces of Jilin and Heilongjiang, optimize the expressway network of the two places, and form another convenient road transportation channel between the two provinces of Heiji and Jilin, and reduce the traffic pressure on the highway around Harbin. Editor/Zhang Jianbing