New Energy
Shock!!! The world's highest power transmission and transformation project has begun in Tibet
Seetao 2019-09-24 11:10
  • The construction of this project will completely end the long history of operation of the isolated power network in ali power grid and provide power guarantee for the overall development strategy and border security of the country
  • With a total investment of 7.4 billion yuan and a transmission line length of 1,689 kilometers, ali and tibetan-china power grid interconnection project is by far the highest and most challenging power transmission and transformation project in the world
The average elevation of the tower is 4572 meters, and the highest elevation is 5357 meters
Reading this article requires
5 Minute

The mobilization meeting for the commencement of the grid interconnection project between ali and Tibet was held in Lhasa, Tibet. The construction of the project will completely end the long history of operation of the isolated network of ali power grid and provide power guarantee for the overall national development strategy and border security. The project is planned to be completed and put into operation in 2021.

The power network project between ali and Tibet is the highest and most challenging power transmission and transformation project in the world so far. The construction environment is extremely harsh and the environmental protection requirements are extremely strict. The average elevation of the tower is 4572 meters, and the highest elevation is 5357 meters. The zaga 220kv substation and 220kv zhongba - hall transmission line are the highest 220kv transmission lines in the world. Engineering 3 times across the Brahmaputra, over 5300 meters above sea level, Ma Youmu mountain, mount Kong Tang lahm crossing permafrost area, and no one less people area, marsh, along the weather, mainland oxygen content is only 50%, 60%, the average temperature 0-5 degrees Celsius, more than 25 degrees Celsius temperature gap between day and night, year period only 6 months, especially at an altitude of 4500 meters above the area less than 5 months valid period, also faces during the permafrost swamp area in winter 120 base iron tower foundation construction of extremely difficult.

The project starts from the dolin 220kv substation in sanzhuzi district of xigaze city and ends at the 220kv barr substation in gar county of ali region, spanning 10 districts and counties of 2 prefectural cities in xizang. The total investment of the project is 7.4 billion yuan, and the transmission line length is 1,689 kilometers. During the peak period of construction, hundreds of participating units will participate in the construction, and the peak period of all participating personnel will reach more than 30,000. Editor/zhao jing


Comment

Related articles

Energy storage

568MW+3.6GWh The largest solar energy storage cluster in Eastern Europe settles in Romania

04-05

New Energy

Why has Romania become a new hotspot for new energy investment in Europe?

04-05

Hydropower

China's hydropower technology innovation welcomes a new platform

04-05

Wind power

Vietnam's REE invests billions of dollars in offshore wind power

04-05

Hydropower

Romania's hydropower expansion sprint: Nehoia ș u 2 project launches bidding

04-04

Wind power

1.422 billion kilowatt hours! Gansu Qinghai Green Power Direct Connection Project Approved

04-03

Collect
Comment
Share

Retrieve password

Get verification code
Sure