On October 28, 2022, the Beijing Construction Engineering Information Network released the bidding announcement for the construction of the station front and four electricity bid sections of the new Chengdu Chongqing Middle Line Railway in Sichuan. The project belongs to the industry railway, and the tenderee is Yangtze River Railway Group Sichuan Co., Ltd., with a total investment of 25.847 billion yuan.

Project overview
The Sichuan section of the newly-built Chengdu Chongqing Middle Line starts from the Sichuan Chongqing provincial boundary and ends at Chengdu Railway Terminal, Chengdu Station. The main line is 188.617km long. 140 bridges with a length of 118.591km and 27 tunnels with a length of 38.368km; The total length of bridges and tunnels is 156.959km, and the proportion of bridges and tunnels is 83.22%; Three new stations will be built on the main line, including Anyue Station, Lezhi Station and Jianzhou Station, and one existing station will be introduced to Chengdu Station; One Shiling South Station will be built in the ordinary speed relocation project of Chengdu Terminal, and the supporting rolling stock facilities will be built. The designed driving speed is 350 km/h, and a comprehensive test section will be built from the provincial boundary to Jianzhou.
technical standard
Railway grade: high-speed railway; Number of main lines: double line; Design speed: 350km/h; Distance between main lines: 5.0m; Maximum gradient: 20 ‰ for general sections and 30 ‰ for difficult sections; Minimum plane curve radius: 7000 m for general sections and 5500 m for difficult sections. Among them, the section from Dazu to Jianzhou New Town is 8500m in general section and 7500m in difficult section; The standard suitable for the driving speed shall be adopted for the section leading into the hub; Traction type: electric power; Locomotive type: EMU; Effective length of arrival departure track: 650m; Train operation control mode: CTCS-3 train control system; Dispatching command mode: centralized dispatching; Other technical standards shall be implemented in accordance with the Code for Design of High speed Railway.

Section division
This bidding is divided into 10 lots, with lot numbers: CYZXSD, CYZXZQ-1, CYZXZQ-2, CYZXZQ-3, CYZXZQ-4, CYZXZQ-5, CYZXZQ-6, CYZXZQ-7, CYZXZQ-8, CYZXZQ-9,
The quantities of CYZXSD project are: power and electrification system integration project, communication, signal, disaster prevention, information, vehicle system integration project, mileage/scope: DK288+400 ballasted and ballastless boundary point~DK102+706 provincial boundary.
CYZXZQ-1, quantities: 0.5 tunnels/4.854km, shield segment prefabrication 10380m, Anyue Plate Factory. Key and difficult projects: Shu'an Tunnel, 4.854km long, mileage/range: DK288+400 ballasted and ballastless boundary point ~ DK282+986 Shu'an Tunnel 250km/h and 350km/h section boundary point.
CYZXZQ-2, the quantities are: 0.718km subgrade, 3 bridges/14.757km, 391 prefabricated box girders, 1.5 tunnels/6.345km. Key and difficult projects: Shu'an Tunnel, 5.526km long; Chengdu Super Major Bridge, 14.235km long, mileage/range: DK282+986 Shu'an Tunnel 250km/h and 350km/h section boundary point ~ DK261+168 Tianziying No. 2 Bridge abutment at Chongqing end.
CYZXZQ-3, the quantities are: 0.413km subgrade, 2 bridges/0.295km, 3 tunnels/15.442km, a simplified plate factory. Key and difficult projects: Longquanshan Tunnel, 8.027km long; Huangjiashi Tunnel, 4.682km long. Qianfeng Chong Tunnel, 2.733km long, mileage/range: abutment at Chongqing end of DK261+168 Tianziying No. 2 Bridge to abutment at Chengdu end of DK245+021 Chengdu Expressway Super Major Bridge.

CYZXZQ-4, quantities: 2.556km subgrade, 13 bridges/16.768km, 491 box girder precasting and erection, 2 tunnels/0.526km, 285.7 double track km. Key and difficult projects: Super large bridge of simplified expressway, 3.046km long; Shipan Grand Bridge, 1.475km long; The super large bridge across Chengdu Second Ring Expressway, 2.992km long; The super large bridge across Chengdu Longjiang Expressway, 2.424km long; The bridge crosses Boxiang Village, with a length of 3.671km; Jianzhou Station, mileage/range: abutment at Chengdu end of DK245+021 Chengdu Jianzhou Expressway Grand Bridge ~ DK225+169 Chengdu end of Tuojiang Grand Bridge, track laying mileage: DK288+400 ballast and ballastless dividing point of Sichuan section ~ DK102+706, and DK2+700 ~ DK102+706 of Chongqing section.
CYZXZQ-5, quantities: 3.577km subgrade, 20 bridges/20.943km, 581 box girder precast and erected. Key and difficult projects: Tuojiang Grand Bridge, 1.254km long; Pingwu No. 2 Grand Bridge, 6.454km long; Super large bridge across the Third Ring Expressway, 2.406km long; Huanxi River Grand Bridge, 3.566km long, mileage/range: DK225+169 Tuojiang River Grand Bridge abutment at Chengdu end to DK200+647 Banzhuyuan Bridge abutment at Chongqing end.
CYZXZQ-6, quantities: 3.679km subgrade, 16 bridges/16.283km, 778 prefabricated box girders, 5 tunnels/2.298km. Key and difficult projects: the super large bridge across Chongqing Chengdu Expressway, with a length of 1.831km; Extra large bridge of Yanbantan Reservoir, 1.972km long; It crosses the super large bridge of Suining Ziyang Expressway, with a length of 1.286km; Wutongcun Bridge, 1.886km long; The super major bridge across Wenfeng Avenue is 2.364km long, with mileage/range from DK200+647 Banzhuyuan Bridge abutment at Chongqing end to DK178+390 Mingjiagou Super Major Bridge abutment at Chengdu end.
CYZXZQ-7, quantities: 6.415km subgrade, 30 bridges/19.736km, 6 tunnels/3.239km. Key and difficult projects: Zongshupo Tunnel, 1.054km long; Yaojiaba Grand Bridge, 4.395km long; The super large bridge across Chengdu Ziyang Chongqing Expressway, with a length of 1.634km; Lezhi Station, mileage/range: DK178+390 abutment at Chengdu end of Mingjiagou Super Major Bridge ~ DK148+996 abutment at Chengdu end of Longqiaogou Super Major Bridge.

CYZXZQ-8, quantities: 3.933km subgrade, 18 bridges/1.004km, 611 prefabricated box girders, 6 tunnels/4.003km. Key and difficult projects: Wenchang Village Tunnel, 2.021km long; The super large bridge across Anyue Avenue, 1.043km long; It crosses Suining Neijiang Expressway Grand Bridge, with a length of 1.393km; Anyue Station, mileage/range: abutment at Chengdu end of DK148+996 Longqiaogou Super Major Bridge to abutment at Chengdu end of DK131+059 Youfanggou Reservoir Super Major Bridge.
CYZXZQ-9, quantities: 6.024km subgrade, 38 bridges/20.665km, 618 prefabricated box girders, 3 tunnels/1.661km. Key and difficult projects: Rongjiawan Tunnel, 1.302km long; Tianliuwan Grand Bridge, 1.65km long; Mawan Grand Bridge, 1.278km long; The super large bridge across Zitong Expressway is 0.788km long., Mileage/range: abutment at Chengdu end of DK131+059 Youfanggou Reservoir Bridge ~ DK102+706 provincial boundary. Keywords: engineering construction, engineering news, engineering construction information
Planned duration: 1825 calendar days, planned commencement date: November 30, 2022, and planned completion date: November 29, 2027.
Acquisition and submission of bidding documents
The Bidder is requested to log in to Beijing Public Resources Trading Platform for Engineering Construction to download the electronic bidding documents from 16:00 on October 28, 2022 to 18:00 on November 2, 2022. Deadline for submission of documents: 09:30, November 21, 2022. Editor/Zhao E