Special
Jiangxi Ganzhou East 500 kV Transmission and Transformation Project Approved
Seetao 2024-02-26 17:34
  • Approval of this power transmission and transformation project will help ensure the stability and reliability of power supply
Reading this article requires
3 Minute

On February 26, 2024, the Jiangxi Provincial Energy Bureau issued a reply on the approval of the Ganzhou East 500 kV Transmission and Transformation Project. The construction content and scale of the project are as follows:

Substation section

A new 500 kV substation will be built in the east of Ganzhou, with a capacity of 2 × 750 MVA. In this phase, there will be 2 500 kV outgoing lines and 4 220 kV outgoing lines.

Ganzhou 500kV Substation Protection Renovation Project and Hongdu 500kV Substation Protection Renovation Project; Construct corresponding secondary system engineering such as communication, protection, and remote control.

Line section

The 500 kV line from Ganzhou to Hongdu is disconnected and connected to the 500 kV substation line project in Ganzhou East. The length of the new line path is 90 kilometers, and the cross-section of the new line conductor is 4 x 630 square millimeters on the Ganzhou side and 4 x 400 square millimeters on the Hongdu side.

The approval of the Ganzhou East 500 kV Transmission and Transformation Project is of great significance for meeting local electricity demand, improving power grid structure, and promoting the development of new energy. At the same time, the construction of the project also needs to fully consider environmental protection, energy conservation and other factors to ensure the sustainable development of the project. Editor/Zhao E


Comment

Related articles

Special

King of Glory Technology: Global Campaign Behind 50 Billion Market Value

12-12

Special

Malaysia becomes the preferred destination for Chinese enterprises to go global

11-21

Special

Revelation from the Counterattack of the 'Chinese Screen'

11-17

Special

What does the future of photovoltaics rely on? Energy storage provides the answer

11-14

Special

Canadian Energy Storage Orders Full, Stock Price Rises Over 40% on 4th

11-10

Special

The real growth of construction machinery overseas in 2025

11-06

Collect
Comment
Share

Retrieve password

Get verification code
Sure