Xinjiang Hami Pumped Storage Power Station Project Investor Tenders
Seetao 2022-04-29 11:06
  • The completion of the project can smooth the output of wind power and photovoltaics, and strengthen the safe operation of the power grid
Reading this article requires
5 Minute

On April 27, 2022, the Hami City Development and Reform Commission issued an announcement on the competitive allocation of investors in the Hami City Pumped Storage Power Station Project. The bidding content includes 4 pumped-storage power station projects with a total installed capacity of 5.4 million kilowatts, the first bid section of the Yushugou 1.4 million-kilowatt pumped-storage power station project, the second bid section of the Yushugou East 1.4 million-kilowatt pumped-storage power station project, and the third bid. The bidding section is Hami West 1.4 million kilowatt pumped storage power station project, and the fourth bidding section Erdaogou 1.2 million kilowatt pumped storage power station project.

Project Overview

Hami pumped-storage power station project investment main body is located in Yizhou District, Hami City. There are 4 pumped-storage power station projects with a total installed capacity of 5.4 million kilowatts, which are divided into 4 bidding sections. The first bidding section Yushugou is 1.4 million kilowatts. Pumped-storage power station project, Yushugou East 1.4 million kW pumped storage power station project in the second bid, Hami West 1.4 million-kilowatt pumped storage power station project in the third bid, and Erdaogou 1.2 million-kilowatt pumped storage power station in the fourth bid power station project.

Obtaining or submitting tender documents

From April 28, 2022 to May 8, 2022, from 10:00 to 14:00 in the morning, and from 16:00 to 19:30 in the afternoon (Beijing time), the bidders will be acquired offline in Hami City, Xinjiang Obtained from No. 17-7, Global International, Tianshan North Road, Izhou District, please bring a valid business license, the original power of attorney of the legal representative, the original ID card of the entrusted person, and the information on the "Credit China" website. There is no serious illegal or dishonest behavior. Screenshot of the information record; if it is a consortium participating in the bidding, it is required to provide the consortium agreement and the business licenses of all parties in the consortium. After passing the review, the bidding documents will be released. The deadline for submission of documents is 10:00 on May 20, 2022. Editor / Zhao E

Comment

Related articles

Energy storage

20GWh new energy storage low-carbon intelligent manufacturing project starts construction

04-18

Hydrogen energy

Invest 5.5 billion! Gansu Jiuquan Green Methanol Project Starts Construction

04-18

Energy storage

Inner Mongolia Halaqin 8.9 billion yuan pumped storage power station promotes construction

04-18

Petrochemical

Yanchang Petroleum partners with Hualu Company to build a new project in Yulin, Shaanxi

04-17

Petrochemical

22 billion! Sinopec Great Wall Energy's coal to olefin project accelerates landing

04-17

Petrochemical

127.4 billion! Shandong's large-scale refining project enters a comprehensive sprint stage

04-17

Collect
Comment
Share

Retrieve password

Get verification code
Sure