On August 17, 2022, the pre-examination of the bidding qualification for the construction of the newly built Shanghai via Suzhou-Huzhou Railway Shengze Station and Nanxun Station, the newly built Huzhou to Hangzhou West to Hangzhou-Huangzhou High-speed Railway Link Project Huzhou East Station and related works. It was announced that the construction of the three stations of the Huzhou East, Nanxun and Shengze stations of the Shanghai-Suhu High-speed Railway will officially start in October and be completed in May 2024.
Project Overview
The construction sites of the new Shanghai-Huzhou-Suzhou-Huzhou railway line from Shanghai Hongqiao to Huzhou are located in Jiangsu Province and Zhejiang Province. The main line is 163.8 kilometers. New stations on the whole line, Songjiang South Station, Liantang Station, Fenhu Station, Shengze Station and Nanxun Station, were built on behalf of Huzhou East Station, and 2 existing stations were used for a total of 8 stations. Mainly set up 1 comprehensive maintenance workshop, 2 maintenance work areas; 1 cargo yard, 1 passenger station, and 1 maintenance turn-back section.
Main technical standards of this project: railway grade: high-speed railway; design speed: 350km/h; number of main lines: double lines; minimum curve radius: 7000m for general sections, 5500m for difficult sections; maximum slope: 20‰; effective length of arrival and departure lines: 650m; train operation control mode: automatic control; dispatch command mode: comprehensive dispatch and centralized.
Division of tenders: It is divided into 3 tenders, as follows:
HSHZF-1 tender section: Shengze station building, platform canopy and related projects, with a total construction area of about 30,000 square meters, of which the station building area is about 12,000 square meters; the platform canopy covers an area of about 7,324 square meters; production and living houses are about 10,770 square meters square meters.
HSHZF-2 lot: Nanxun station building, platform canopy and related projects, with a total construction area of about 24,400 square meters, of which the station building area is about 15,000 square meters; the platform canopy covers an area of about 7,324 square meters; production and living houses are about 2,098 square meters .
HSHZF-3 lot:
Construction of Hu-Hangzhou Railway Project: Huzhou East Station Station Building, platform canopy and related projects. The station construction area is about 20,958 square meters, of which the station building area is about 14,995 square meters, the overhead floor is about 5,963 square meters, and the platform canopy covers an area of about 16,335 square meters. ; The area of the elevated driveway and the canopy above the driveway is about 7286 square meters; the production and living houses are about 3000 square meters. Keywords: engineering news, engineering construction information, engineering construction
Shanghai-Suhu Railway Line Project: The area of production and living houses on the Hu-Suhu Line is about 4,347 square meters.
Planned Duration
The planned construction period of the HSHZF-1 and HSHZF-2 tenders: 600 calendar days, the planned start date: October 1, 2022, and the planned completion date: May 22, 2024.
HSHZF-3 standard project duration: 426 calendar days. Planned start date: October 1, 2022, planned completion date: November 30, 2023.
Submission of Prequalification Documents
The prequalification application documents are submitted from 8:30 on September 1, 2022 to 9:30 on September 1, 2022, and the deadline is 9:30 on September 1, 2022, and the location is Nanjing Public Resources Trading Center North Gate.Editor/Zhao E