Announced in the project in front of the Yuwan high-speed railway station
Seetao 2022-09-26 10:23
  • The planned construction period of this project is 4.5 years, and the planned start date is October 31, 2022
  • The main line of the project is 250.91 kilometers long, divided into 9 bidding sections, and the project investment is about 26.6 billion
Reading this article requires
16 Minute

On September 24, 2022, the candidates who won the bidding for the construction of the new Chongqing-Wanzhou high-speed railway station front project were announced and released. The Chongqing-Wanzhou high-speed railway project will officially start construction in October, with a planned construction period of 4.5 years.

Project Overview

The new Chongqing-Wanzhou high-speed railway line has a total length of 250.91 kilometers. The line leads from the Chongqing hub and runs eastward along the Yangtze River through Banan, Fuling, Fengdu, Zhongxian and Wanzhou. Among them, Fuling North Station and Wanzhou North Station are existing stations. Chongqing East Station is under construction, Fengdu North Station and Zhongxian Station are newly built stations.

Planned construction period: 4.5 years, planned start date: October 31, 2022, planned completion date: April 30, 2027.

Tender division and bid winning candidates

Chongqing East Railway Station to Wanzhou North Railway Station, DK14+233.2 ~ DK250+100 works in front of the station; the bidding budget is about 26.7 billion yuan. This tender is divided into 9 tenders.

CQWZZQ-1, the number of projects is: total length of 33.01km, of which 8 tunnels/22.36km, 15 bridges/8.97km, and roadbed 1.68km; the total proportion of bridges and tunnels is 95.0%. Xiangshui Town Beam Field, responsible for the prefabrication of the 301-hole box girder in the DK27+720-DK56+136 section, and the prefabrication of the small components in the DK0+000-DK56+136 section.

Mileage/range: DK14+233.2~D1K47+550.4 Huangni Village Double-Line Bridge Chongqing Duan Abutment ~ Yehe Town Double Line Super Bridge Wanzhou Duan Abutment.

The first winning candidate for this tender section: China Railway Eleventh Bureau Group Co., Ltd., the evaluated bid price: 3.173 billion yuan.

CQWZZQ-2, the number of projects is: total length of 33.44km, including 6 tunnels/21.69km, 17 bridges/7.93km, and roadbed 2.94km; the total proportion of bridges and tunnels is 88.6%. Zhongxian station yard project, the length of the station roadbed is 0.88km. Zhongxian Liangchang is responsible for the prefabrication of 190-hole box girder in sections DK63+464~DK88+316, and the prefabrication of small components in sections DK56+136-DK88+316. Mileage/range: D1K47+550.4~D1K80+989.2 Yehe Town Double-Line Super Bridge Wanzhou Duan Abutment~Caoxiba Double-Line Bridge Wanzhou Duan Abutment.

The first winning candidate for this tender section: China Railway 18th Bureau Group Co., Ltd., the evaluated bid price: 3.401 billion yuan.

CQWZZQ-3, the number of projects is: total length of 36.05km, including 6 tunnels/12.83km, 31 bridges/14.56km, and roadbed 7.77km; bridges and tunnels account for 78.5% of the total. Guantangxi Liangchang is responsible for the prefabrication of the 496-hole box girder in the DK93+185-DK131+367 section, and the small component prefabrication in the DK88+316-DK131+367 section. Mileage/range: D1K80+989.2~DK117+036.604 Caoxiba Double-Line Bridge Wanzhou End Abutment~Caofang Double-Line Bridge Wanzhou End Abutment.

The first winning candidate for this tender section: China Railway Third Bureau Group Co., Ltd., the evaluated bid price: 3.041 billion yuan.

CQWZZQ-4, the number of projects is: total length of 33.4km, including 7 tunnels/17.68km, 20 bridges/10.63km, and roadbed 4.56km; the total proportion of bridges and tunnels is 86.3%. Fengdu station project, the station roadbed length is 0.52km. Lujiazhai Liangchang is responsible for the prefabrication of the 153-hole box girder in the DK141+706-DK150+434 section, and the prefabrication of the small components in the DK131+367-DK150+434 section. Mileage/range: DK117+036.604~DK150+433.312 The abutment at the end of Wanzhou side of the double-track bridge in the slot house to the abutment at the end of the Chongqing side of the double-track super bridge in Quxi Village.

The first winning candidate for this tender section: China Railway Seventeenth Bureau Group Co., Ltd., the evaluated bid price: 3.239 billion yuan.

CQWZZQ-5, the number of projects is: the total length of 32.43km, of which 13 tunnels / 15.56km, 20 bridges 9.65km, roadbed 7.20km; the total proportion of bridges and tunnels is 77.8%. Xiaoguzhai Liangchang is responsible for the prefabrication of the 206-hole box girder in the DK151+184-DK182+835 section and the prefabrication of the small components in the DK150+434-DK182+835 section. Mileage/range: DK150+433.312~DK182+834.643 Chongqing end abutment of Quxi Village double-track super bridge~Chongqing end abutment of Caijiagou double-track super bridge.

The first winning candidate for this tender section: China Railway Construction Bridge Engineering Bureau Group Co., Ltd., the evaluated bid price: 3.383 billion yuan.

CQWZZQ-6, the number of projects is: total length of 7.07km, including 4 single-track tunnels/7.25km, 4 single-track bridges of 2.56km, and roadbed 3.51km. The Fuling North Station Reconstruction Project and the Yuyi High-speed Railway were implemented simultaneously. Fuling North and Fengdu North sleeper factories are responsible for supplying the prefabrication of double-block sleepers for the entire line, and are responsible for the prefabrication of small components in DK182+835-DK186+450 sections. Fuling North Track Laying Base is responsible for the entire track laying project. Mileage/range: DK182+834.643~D1K189+908.444 Caijiagou Double-Line Super Bridge Chongqing End Abutment to Sandouqiu Double Line Super Bridge Wanzhou End Abutment.

The first winning candidate for this tender section: China Railway First Bureau Group Co., Ltd. The evaluated bid price: 2.244 billion yuan.

CQWZZQ-7, the number of works: Shituo Yangtze River Bridge. Mileage/range: DK202+204.050 ~ DK203+620.950, the length of the lot is 1.417km.

The first winning candidate for this tender section: China Railway Bridge Bureau Group Co., Ltd., the evaluated bid price: 1.95 billion yuan.

CQWZZQ-8, the number of projects is: the total length of 29km, of which 5.5 tunnels/19.87km, 12 bridges/7.46km, roadbed 1.67km; the total proportion of bridges and tunnels is 94.2%. Shuimo Tanliang Field is responsible for the prefabrication of the 162-hole box girder in the DK186+450-DK202+460 section, and the prefabrication of the small components in the DK186+450-DK220+323 section. Mileage/range: D1K189+908.444 Sandouqiu Double-Line Super Bridge Wanzhou Duan Abutment to Changlinggang Tunnel Entrance (4643m), excluding Shituo Yangtze River Bridge.

The first winning candidate in this tender section: China Construction Eighth Engineering Bureau Co., Ltd., the evaluated bid price: 2.833 billion yuan. Key words: engineering construction information, engineering news, engineering construction

CQWZZQ-9, the number of projects is: total length of 29.873km, including 4.5 tunnels/22.05km, 8 bridges/6.02km, and roadbed 1.60km; the total proportion of bridges and tunnels is 94.6%. Banan Liangchang is responsible for the prefabrication of the 184-hole box girder in the DK229+017-DK252+901 section, and the small component prefabrication in the DK220+323-DK255+800 section. Mileage/range: DK220+227.000~DK250+100.000 Changlinggang Tunnel Exit~Jianzishan Tunnel Exit.

The first winning candidate for this tender section: China Railway 12th Bureau Group Co., Ltd., the evaluated bid price: 3.39 billion yuan. Editor/Zhao E

Comment

Related articles

Central enterprises

The 12th Hydropower Bureau and the Zhejiang Emergency Department build a rescue alliance

08-19

Central enterprises

XCMG Group and Rio Tinto Group sign a global cooperation framework agreement

08-15

Central enterprises

China Power Construction and State power Investment leaders to deepen energy cooperation

07-20

Central enterprises

China Construction Third Engineering Bureau Zhejiang Transportation Project

07-18

Central enterprises

5.635 billion yuan! China Energy Construction won the bid for Jinneng Phase III project

07-15

Central enterprises

National Railway Administration and Chongqing City Sign Cooperation Agreement

07-04

Collect
Comment
Share

Retrieve password

Get verification code
Sure