Gezhouba No.2 Ship Lock Completed Maintenance and Resumed Navigation Early
Seetao 2026-04-15 14:58
  • This move will ensure smooth navigation along the Yangtze River and improve the efficiency of the Golden Waterway
Reading this article requires
2 Minute

At 20:00 on April 12, 2026, as the Shenjia 898 ship carrying 4250 tons of cargo slowly entered the Gezhouba No.2 Ship Lock, it marked the successful completion of 20 originally scheduled maintenance projects after nearly 40 days of planned suspension. The Gezhouba No.2 Ship Lock officially resumed navigation, 12 hours ahead of schedule.

Since the major overhaul at 8:00 am on March 4, 2026, the Three Gorges Bureau has prepared in advance, organized carefully, and strictly controlled on-site safety, engineering quality, and progress milestones. We have developed and utilized a series of new equipment, processes, and technologies, such as the synchronous lifting system for the herringbone gate and the maintenance fixture for the plunger pump, to assist in improving the quality and efficiency of major repairs, achieving the overall goal of "meeting the 304 standard".

This article is reprinted in: Three Gorges Navigation Editor/Gao Xue

Comment

Related articles

News

Mozambique President 'Check in' Hunan Intelligent Manufacturing!

04-21

News

Forward looking clean energy layout for future energy

04-20

News

Cracking the Deep Sea Wind Power Grid Connection Challenge

04-20

News

Electricity installed capacity ranks first in the world

04-20

News

Gui'an New Area breaks through the new paradigm of collaborative computing

04-17

News

Abu Dhabi Crown Prince Meets with Leaders of Chinese Leading Enterprises

04-17

Collect
Comment
Share

Retrieve password

Get verification code
Sure