Build a building in 4 months! China Mobile's Zhongwei Data Center Accelerates Running
Seetao 2026-07-16 14:28
  • China Mobile B Zone B07 Data Center Building launches EPC bidding, taking only one quarter from start to operation
Reading this article requires
6 Minute

On July 15, 2026, the EPC bidding announcement for Building B07 in Zone B of China Mobile (Ningxia Zhongwei) Data Center was posted online, requiring delivery before December 15, 2026, with a total construction period of only 123 days. This 3-story steel structure building has a construction area of approximately 17000 square meters and is integrating into the computing power map being developed by Zhongwei in a competitive manner.

Steel structure grabbing speed

The B07 computer room building adopts a steel structure form, with 3 floors, a floor height of 7.3 meters, a total height of about 23.76 meters, and a building area of about 170000 square meters. The bidding scope covers all tasks of survey, design, procurement, and construction, with a planned total construction period of 123 calendar days -16 days for design and 123 days for construction. The project is scheduled to commence on August 15th and be delivered on December 15th. The rhythm of starting construction and delivering in the same year places high demands on the integration of design and construction capabilities.

This bidding is for the EPC project of the second data center building in Zone B, which was released in July. Zone B plans to construct 6 data center buildings and 2 maintenance support buildings, with a total investment of 6.149 billion yuan and a total load of 245.2 megawatts, capable of accommodating approximately 13624 physical cabinets. The bidding for Building B07 is a concrete manifestation of the accelerated progress of this plan.

High computing power of central defense accelerates formation

China Mobile has accumulated over ten years of layout in Zhongwei, Ningxia. It has built 10 data centers and delivered 80000 standard racks, with a rack sales rate of 100%. At present, the dispatchable computing power exceeds 60000 PFLOPS, and the price remains stable at 0.36 yuan/kWh. The cost advantage of the green power direct supply mode is particularly prominent. Keywords: data center, computing infrastructure

In the first half of 2026, the total bidding scale related to intelligent computing of the three major telecom operators is about 15.758 billion yuan, with China Mobile leading with about 9.256 billion yuan, accounting for nearly 60%. As a hub node for both Eastern and Western computing, Zhongwei will have a total of 230000 standard racks and a computing power scale of 130000P by 2025. Building B07 is just one node in Zhongwei's expanding computing power map, but its 123 day schedule reveals that computing infrastructure is shifting from annual to daily operations.Editor/Cheng Liting

Comment

Related articles

Computing Power

China Telecom's 30 billion yuan deployment of chief triangulation computing power

07-16

Computing Power

The transformation of a data center on a piece of land in Cape Town

07-16

Computing Power

14nm AI chip unveiled in Shanghai, with computing power reaching 520 trillion times

07-15

Computing Power

The growth rate of China's artificial intelligence related industries will exceed 30%

07-15

Computing Power

5 billion euros bet on Ireland, Intel's computing power bet

07-15

Computing Power

Intelligent Computing Project Lands in Guangxi to Consolidate AI Power Infrastructure

07-14

Collect
Comment
Share

Retrieve password

Get verification code
Sure