On November 15, 2026, the annual cumulative power generation of Tiantai Pumped Storage Power Station in Zhejiang Province officially exceeded 1.7 billion kilowatt hours. This is the first fully operational pumped storage power station in China during the 15th Five Year Plan period, and has completed the practical test of domestic ultra-high head and large capacity units with real operating data.

724 meter head unit undergoes high-frequency working condition inspection

The first unit of Tiantai Pumped Storage Power Station will be connected to the grid for power generation in December 2025, and the last unit will complete a 15 day assessment and trial operation in June 2026 to achieve full capacity production. As of mid November 2026, the four units have accumulated approximately 4159 hours of power generation and 5020 hours of pumping operation, completing a total of 773 power generation and 847 pumping operations.

The first domestically produced pumped storage unit with a rated head of 724 meters and a single unit capacity of 425000 kilowatts has maintained stable operation through continuous frequent start stop and condition switching. The unit's output capacity, operating efficiency, and equipment reliability have fully met the design requirements, marking that China has fully mastered the complete set of key technologies for ultra-high head and large capacity pumped storage units.

Continuous full load supply guarantee during the transition from summer to winter

In the critical stage of ensuring power supply during the peak summer of 2026, the power station operation and maintenance team will conduct encrypted equipment inspections throughout the entire process, monitor the real-time operation status of the units 24 hours a day, and respond quickly during the peak period of electricity load in Zhejiang power grid, providing key support for the regional power grid to smoothly pass the summer electricity peak. Keywords: pumped storage power station, new energy

Entering the peak winter cycle of 2026, the power station will continue to operate at full capacity, quickly switching operating conditions during periods of new energy output fluctuations, smoothing out grid frequency fluctuations, and enhancing the space for wind and solar power consumption. As an important peak shaving and energy storage node of East China Power Grid, Tiantai Pumped Storage Power Station will continue to release its capacity value in the future, providing stable and flexible regulation capabilities for the construction of a new power system in Zhejiang and supporting the continuous promotion of regional energy green and low-carbon transformation.Editor/Cheng Liting

Comment

Related articles

Energy storage

The UK has built the largest battery energy storage power station in Europe

11-18

Energy storage

New energy storage power station starts construction on Gobi Desert

11-18

Energy storage

The first grid connection of Inner Mongolia Adan's new energy project to Ukraine

11-16

Energy storage

Bid Winners Announced for Jiangxian Mixed LFP Energy Storage System

11-15

Energy storage

China's largest polyanion sodium battery base capped in Ningxia

11-14

Energy storage

Pumped storage power station starts construction, Qinghai adds clean energy regulator

11-13

Collect
Comment
Share

Retrieve password

Get verification code
Sure