On the evening of November 20, 2026, the lights of the International Business Department of CNOOC Engineering were on, and the team repeatedly checked the contract terms sent by Qatar Energy Company. With authorized representatives from both parties signing the document, a marine engineering general contract worth approximately $800 million has been officially finalized. This is another big deal won by CNOOC Engineering in Qatar.

Winning the Qatar Grand Contract Again
The contract amount is about 800 million US dollars, equivalent to approximately 5.6 billion Chinese yuan. CNOOC Engineering will undertake the entire process of project management, detailed design, equipment procurement, construction, transportation, offshore installation, and pre commissioning. Qatar Energy Company shall make monthly payments for the project based on the actual construction progress. This is another large-scale offshore engineering contract signed by CNOOC Engineering in Qatar, following the previous $4 billion Bohani oil field project.

Laying over 100 kilometers of pipelines
The project is located in the Maidan Mahzam offshore oil field in Qatar, which is about 100 kilometers northeast of the Qatar coast and has a water depth of about 40 meters. It was put into development in the 1960s. CNOOC Engineering is responsible for the second section, with a focus on laying over 100 kilometers of submarine pipelines, power cables, and umbilical cables, as well as installing related offshore facilities. The first section was obtained by a consortium consisting of Vietnamese and Singaporean enterprises, involving the construction of new production platforms and the renovation of existing facilities. Keywords: the Belt and Road News Network, Middle East, enterprise industry, offshore oil and gas

Five and a half years of construction progress
The contract construction period is 66 months, approximately five and a half years. CNOOC Engineering needs to complete all stages from design and procurement to offshore installation and commissioning. The main engineering value of the oilfield redevelopment plan is estimated to be between 4 billion and 5 billion US dollars. In recent years, CNOOC Engineering has won consecutive large orders in the Qatar market, including the Bohani oil field project that started construction in September 2026, as well as the liquefied natural gas project that was previously won jointly with an Italian company. In the first three quarters of 2026, CNOOC Engineering achieved a revenue of 19.461 billion yuan and a net profit attributable to the parent company of 1.68 billion yuan.Editor/Gao Xue