Shangyi Xiaoyanigou Phase 5 240MW wind storage project started smoothly
Seetao 2024-05-12 11:05
  • The start of the project is the starting point of the project, which lays a solid foundation for the smooth progress of the project
Reading this article requires
5 Minute

On May 10, 2024, Shangyi Xiaoyanigou Phase 5 240MW wind storage integration project ushered in an important milestone, and the first steel plate produced by Johnson Branch officially began cutting, which marked the official start of construction of the project and the project was progressing smoothly.

Shangyi Xiaoyanigou Phase 5 240MW wind storage integration project plans to install 33 110-meter wind turbines manufactured by Dongfang Electric. Each of these turbines has a capacity of 6.7MW and a maximum blade diameter of 5 meters, while the total height of the entire fan is up to 110 meters. These technical specifications ensure efficient operation of the project and strong power generation capacity.

In view of the urgent project period, in order to ensure the timely completion of the project, the branch carefully planned and took effective measures, sent a special person to the steel plate factory and flange factory to communicate and coordinate, urge the supply progress, ensure that the steel plate, flange and other key raw materials can be delivered on time, laying a solid foundation for the smooth start of the project. Before the start of the project, Al Qaeda organized the workshop production personnel to deeply learn the production technical specifications of the project tower, requiring each employee to strictly comply with the process requirements in the manufacturing process. Strictly control the size, appearance and non-destructive testing of raw materials into the factory to ensure that the quality of raw materials meets the standards, so as to ensure the overall quality of subsequent products.

Techan Branch will scientifically dispatch production resources, efficiently manage the staff team, and further strengthen service orientation and quality management, committed to ensuring the timely delivery of Shangyi Xiaoyanigou Phase 5 240MW wind storage integration project, and take this opportunity to contribute our strength to the construction of the fourth Bureau equipment brand, and jointly create a more brilliant tomorrow.Editor/Zhang Liyuan

Comment

Related articles

Energy storage

Malaysia's South Johor launches Southeast Asia's largest solar energy storage complex

12-04

Energy storage

Shell Energy Europe signs large-scale energy storage agreement with Sunotec

12-03

Energy storage

The energy storage market in the UK is set, and Atlas has won a strong bid

12-03

Energy storage

Canadian subsidiary wins UK large-scale new energy project

12-03

Energy storage

iangxi Yongxin Pumped Storage Power Station solves the problem of new energy consumption

12-03

Energy storage

Bidding for Underground Pumped Storage Power Station Project in Shandong Province

12-02

Collect
Comment
Share

Retrieve password

Get verification code
Sure