At 11:17 am on December 5, 2024, CGN's 260 MW wind farm located in Xipingfang, Jiange, Sichuan successfully achieved full capacity grid connected power generation. The project has an installed capacity of up to 260 megawatts and a total investment of 1.496 billion yuan, which is a major milestone for CGN in the field of new energy.
Since the project started construction in October 2023, the CGN project team has always adhered to the core concept of "safety first, quality first, and pursuit of excellence". Faced with the arduous challenges of transporting large equipment in mountainous areas and the unfavorable conditions of rainy season construction, the project team successfully overcame the difficulties and achieved the predetermined goals through a series of measures such as scientific construction management and efficient resource allocation. Not only did it ensure the safety and quality of the project, improve construction efficiency, but it also demonstrated the outstanding contribution and strong execution ability of the CGN project team, and contributed valuable strength to promoting the development of green energy in China and even globally, demonstrating CGN's responsibility and commitment as a leading enterprise in China's new energy field.
After the project is completed and put into operation, it is expected that the annual power generation of the wind farm will reach 478.9 million kilowatt hours. This achievement means that it can replace approximately 144000 tons of standard coal consumption annually, while significantly reducing greenhouse gas emissions. It is expected to reduce carbon dioxide emissions by approximately 387400 tons, making a significant contribution to environmental protection and energy conservation.
To ensure the smooth operation of the wind farm, the project team and operation and maintenance team of CGN will conduct comprehensive inspections, covering all construction details and equipment operation status, to ensure that every link reaches the optimal state, and to efficiently promote the process of line debugging and grid connection. The successful grid connection of CGN Sichuan Jiange Xipingfang Wind Farm marks another solid step for CGN in the field of new energy, and will continue to contribute clean and reliable green energy to society, helping to achieve carbon neutrality goals.(This article is from the official website of Jian Dao www.seetao.com. Reproduction without permission is prohibited, otherwise it will be prosecuted. Please indicate Jian Dao website+original link when reprinting.) Jian Dao website strategy column editor/Miao Ting
Comment
Write something~