In the early morning, the Ayaguz grassland was covered in frost, and the road roller rolled over the new roadbed. The technician took soil samples to check the compaction degree, but the main beam of the newly made bridge in the prefabrication yard was still wet. To the east is the border. On November 16, 2026, the Ministry of Transport of Kazakhstan announced that the 303 kilometer Bakht Ayaguz railway will proceed as planned and be completed and put into operation in 2027, becoming the third railway border port between China and Kazakhstan with a designed annual freight capacity of up to 20 million tons.
Why do we need to repair it? The answer is at the old port: due to the different track gauges between China and Kazakhstan, each container has to be lifted and replaced, and the capacity for replacement is the bottleneck. The Alataw Pass Dostec was put into use in the early years, and Khorgos Altenkol was later replaced. The two places carried the main flow for a long time.

After the rise of the Middle Corridor across the Caspian Sea, Kazakhstan listed logistics as a national strategy and included the new route in its State of the Union address.
The Harbin side previously reported that the railway freight volume in the first ten months of 2026 increased by 8% year-on-year, with a total of 31.8 million tons, and the diversion has reached a critical window.
Sprint before laying tracks
Official announcement: The total earthwork volume is 39.5 million cubic meters, of which 36.8 million cubic meters have been completed, with a completion rate of 93%. The remaining amount is concentrated in the border areas and around Bakht Station. On site, a special inspection is being conducted on the leveling of the top layer of the roadbed and the compaction degree of the soil, in preparation for the laying of the upper structure of the track. 245 out of 267 culverts have been completed, 12 out of 19 animal husbandry dedicated channels have been completed, and 43 out of 47 planned bridges are under construction. To shorten the delivery cycle, all bridge main beams are produced on-site and undergo third-party certification and full process quality control in accordance with Kazakhstan's national building standards. The project has entered the stage of bridge and culvert completion and preparation before track laying. The key variables for opening in 2027 are the remaining progress of the border section.

Leave the order locally
All track materials are locally sourced: rails are sourced from Aktobe Rail and Profile Factory, concrete sleepers and fasteners are sourced from RWS Binding, Innotrack, Fasteners 2metall (BENT), and Magnetik, and turnouts are supplied by Prommashkomplekt; The material reception and global distribution are located at Ayaguz station. 100% local procurement, directly driving the local steel and rail transit equipment industry chain; The Barktu Port in China is simultaneously upgrading its public rail intermodal hub, and the dual parks of the two countries are being laid out in advance.
Can the delivery of the follow-up track laying phase match the 2027 milestone.
Reduce the burden on the old port
The new line has been put into operation, directly reducing the burden on Dostek and Alten Kohler, and releasing new capacity. It is connected to the existing road network in Ayaguz, and to the north, it can connect major sources of grain, ore, timber, and other goods from northern Kazakhstan and western Siberia, Russia.

The Ministry of Transport of Kazakhstan stated that after being put into operation, it will expand local exports, increase the supply of advantageous products to China, attract cross regional transit cargo flows, and strengthen bilateral economic and trade cooperation. Based on a designed annual transportation capacity of 20 million tons, it is equivalent to adding a sizable export channel beyond the two old ports. The follow-up focus will be on the ramp up speed of transportation volume after being put into use in 2027, as well as the proportion structure of transit and domestic export sources.keywords:Engineering infrastructure
The soil samples are still being sent for inspection. We will have an answer when the first train departs from Bakht and the cargo flow is redistributed.Editor/Yang Meiling