There are new developments in the Jinan Metro Phase II planning project
Seetao 2021-01-14 11:49
  • In 2021, Jinan will actively promote the construction of rail transit and other projects
Reading this article requires
9 Minute

On January 12, 2021, the third meeting of the 17th People's Congress of Jinan City opened. In the 2021 government report, it was mentioned that efforts should be made to optimize the modern transportation system, including subway construction. Looking back at the "Thirteenth Five-Year Plan", the construction plan for the first phase of Jinan Metro has been completed, Line 1 and Line 3 have been officially put into operation, and Line 2 has also achieved trial operation. So, what is the progress of the 6 lines of Line 3, Phase 2, Line 4, Line 6, Line 7, Phase 1, Line 8, and Phase 1 of Line 9 in the second phase of the plan?

Line 3 Phase II Project

The second phase of Line 3 has basically completed the pre-construction preparations and will start construction soon. It is understood that the second-phase project of Line 3 starts from the first-phase project Tantou Station in the south and runs along the Airport Road to the Yaoqiang Airport Station in the north. The line is about 12.9 kilometers long, all of which are underground. As an extension of the first-phase project of Line 3, after the project is completed, it will strengthen the efficient interconnection between the Yaoqiang Airport, the Airport Industrial Economic Zone and the central city, and further play the role of the Yaoqiang Airport as a transportation gateway for the province.

Phase 1 of Line 4

According to the relevant person in charge, the construction permit has been obtained for the first phase of Line 4 and construction is about to start. It is reported that the first-phase project of Line 4 starts from Xiaogaozhuang Station in the west, runs along Qingdao Road, Shun'an Road, Jingshi Road, Tangye Middle Road, and ends at Pengjiazhuang Station in the east. The length of the line is about 40.2 kilometers, all of which are underground.

Line 6 and Line 8 Phase I Project

On January 12, the third meeting of the 17th People's Congress of Jinan City opened. The work report proposed that the construction of the first phase of rail transit lines 6 and 8 will be started in 2021. It is reported that Line 6 starts at Lizhuang Station in the west, along Medicine Avenue, the central axis of Jinan West Station, Jingyi Road, Minghu West Road, Daminghu Road, Shanda South Road, the east-west axis of the International Financial City, Xinluo Street, Fenghuang Road, Walk along the front street of Jinan Xindong Station, east to Liangwangdong Station. The length of the line is about 39.1 kilometers, all of which are underground lines.

The first-phase project of Line 8 starts from Xingcun Station in the west and ends at Shandong University Station in the east. It passes through two administrative districts, the urban area and Zhangqiu District, and mainly runs along Jingshi Road and Jingshi East Road. The total length is 22.6 kilometers, including 14.1 kilometers of overhead lines and 8.5 kilometers of underground lines.

Line 7 Phase I Project

Currently, the first phase of Line 7 has been approved. The project starts from Fenghuang South Road Station in the south, along Tourism Road, the central green axis of the International Financial City, Huayuan Road, Lishan Road, the central axis of the pilot area north of the Yellow River, and north to Jibei Station. The length of the line is about 30.0 kilometers, of which the overhead line is 4.8 kilometers, and the rest is underground.

Phase 1 of Line 9

The first-phase project of Line 9 starts at the South Bank Station of the Yellow River in the west, along Shengli Road, Jinyu Avenue, Xiangquan Road, and Ganghua Road, and ends at Maozhuang Station in the east. The length of the line is about 14.8 kilometers, all of which are underground. Currently, the project has been approved.

It is understood that after the completion of the first phase of Line 9, it will serve the passenger flow distribution in Huashan area and Xindong station area, and efficiently connect rail transit lines 3, 6 and 7 to further strengthen the radiation of the pilot area to the east area of Jinan. , To strengthen the connection between the pioneer area and major transportation hubs such as Jinan East Railway Station and Yaoqiang Airport. Editor/He Yuting

Comment

Related articles

Transportation

The Gulf Railway will be fully operational by the end of 2030

05-21

Transportation

The second phase of the Yangtze River Estuary South Channel has been approved

05-20

Transportation

Saltillo to Nuevo Laredo passenger railway wins 14.4 billion pesos contract

05-19

Transportation

Melbourne SRL project enters the fast lane of construction

05-19

Transportation

Guangzhou Port Nansha Phase V fully starts construction

05-18

Transportation

The first box girder of Hezhan high-speed railway has been successfully erected

05-18

Collect
Comment
Share

Retrieve password

Get verification code
Sure