Recently, the construction of the B1 and C1 workshops of the first phase of the intelligent manufacturing basic parts industrial cluster project located in Chenliang Village, Guiyang Economic and Technological Development Zone has successfully entered the countdown to completion. middle.

At the construction site of the project, the master workers are busy and orderly carrying out the construction of the partition wall inside the factory building, the removal of scaffolding, and the construction of the secondary structure. Project manager Yang Renfei carefully inspected the safety, quality and progress of the site, and told the author with great interest that the project will officially start construction in June 2022. It is an EPC project with a construction area of about 25,800 square meters meters, and the cost is about 89 million yuan. Chengdu Branch of The Fourth Construction Engineering Co., Ltd. of Guizhou Construction Engineering Group undertook and completed the project independently from preliminary design to project construction to interior decoration and installation of facilities and equipment. If all goes well, the entire project is expected to be completed and put into use in the second half of 2023.

According to the on-site technicians, the project design and construction are integrated, and the requirements for the management team are relatively high. The on-site personnel must not only be familiar with the work content of the design and construction phases, but also prepare budget lists, internal audits, external audits, etc. Proficiency and understanding. The project management team thinks in one place, works hard in one place, brainstorms, learns from each other's strengths, and strives to ensure that the procedures, materials, and procedures of the project are legal, compliant, and perfect while strictly controlling key links such as safety, quality, and progress. , Complete, to ensure that the project is always high-quality, high-quality, high-efficiency construction.

Yang Renfei said that during the entire construction process of the project, safety, quality, and progress management have always been planned beforehand, inspected during the event, summarized after the event, tracked during the process, implemented responsibilities, and more specific goals. At the same time, continuously strengthen the training of on-site construction personnel and disclosure of safety and quality, establish quality hidden danger registration and rectification accounts, and regularly eliminate accounts and accounts, and constantly consolidate the foundation of the whole process management. Especially since the "3.25" meeting of the group company was held, the project has further strengthened the implementation of visual identification, visual image, physical measurement and other work and achieved good results. Evaluation and full affirmation, the group's monthly inspection and actual measurement of the pass rate of the steel bar protection layer of columns and beams reached 100%.

It is particularly worth mentioning that during the construction of this project, the project department also actively promoted the practice and application of new technologies and new processes. In addition to the "three-level safety education" and the actual measurement of key parts, and timely follow-up inspections, all new-type buckle-type scaffolding and outer frame construction are used to achieve safe construction, easy installation, and beautiful appearance. In the interior of the building, it actively responded to the call of the provincial party committee and the provincial government. The internal partition walls were all plastered and masonry with phosphogypsum materials, so that environmental protection and architecture complement each other and complement each other.

"Another distinctive construction highlight is that we have actively introduced a new method of connecting steel bars, using mechanical sleeves to connect the steel bars, and threading the joints of the steel bars for fixation. It is more efficient, more convenient and safer to perform lashing," Yang Renfei said.
In order to strengthen the scientific management and control of the site and improve the effectiveness of inspections, the project department also specially set up a monitoring room, and installed "five guns and two balls" camera probes on the construction site, so that there are no dead ends in site management, no loopholes in safety and quality, and high-quality project construction. , High safety and high efficiency.

Yang Renfei said: "While we organically combine manual inspection and on-site monitoring, we also continue to strengthen the construction of smart construction sites, actively build a smart construction site platform, and use scientific and technological innovation to monitor on-site dangerous and major projects, key positions, labor real-name system, and environmental supervision. Effective management and control of tower crane safety supervision, automatic car washing system, etc., and continuous improvement of management level and capabilities, so that the project construction will always move forward along the normal and efficient goals." Editor / Zhao E