New infrastructure
Ganjiang Gannan project approved in 20 days
Seetao 2026-08-05 10:45
  • A ultra-high voltage transmission line, completed the approved route in 20 days
Reading this article requires
6 Minute

When the green power in the Tengger Desert is about to cross mountains and rivers to Jiangxi, Gannan Power Grid is faced with the embarrassment of being able to get in and not fall behind - the transmission capacity of the north-south section is only 3.2 million kilowatts, unable to bear the east wind. Recently, a paper of approval from the Jiangxi Provincial Development and Reform Commission has opened the deadlock. The 1000 kV Ganjiang to Gannan AC power transmission and transformation project has been officially approved, and it only took 20 days from approval application to obtaining approval.

7.2 billion yuan project activates Gannan power grid

As the first approved ultra-high voltage AC project in the Central China region during the 15th Five Year Plan period, the total investment in the feasibility study is 7.218 billion yuan, and it is expected to be completed by 2028. The project will build a 1000 kV Gannan substation with a transformer capacity of 6 million kVA; Build a double circuit 1000 kV AC line from Ganjiang to Gannan, with a length of 298.9 kilometers each, passing through Nanchang, Fuzhou, Ji'an, and Ganzhou.

After being put into operation, the maximum transmission capacity of the Gannan section will increase from the existing 3.2 million kilowatts to 6.5 million kilowatts, more than doubling. This means that the clean electricity sent by the Tengger Jiangxi Ultra High Voltage Direct Current Project can truly be obtained and transmitted, while also facilitating the export of new energy to the southern Jiangxi region.

The central Chinese Japanese ring network extends southward

The Nanyang Zhumadian project was approved and launched in 2018, and the Wuhan Huangshi Nanchang project will be put into operation in 2024. The Central China Japanese style ultra-high voltage AC ring network has gone through a six-year construction period. The Ganjiang Gannan project is a key longitudinal extension of this ring network to the south, which will further improve the Central China ultra-high voltage network and enhance the regional inter provincial power mutual aid and consumption capacity. Keywords: kV substation, ultra-high voltage

Approval is just the starting point. When the structure of the Gannan substation is erected on the red soil, the north-south section of the Jiangxi power grid is truly connected.Editor/Cheng Liting

Comment

Related articles

New infrastructure

Beijing-Tianjin-Hebei Expands High-Quality Green Power Trading to Boost Green Development

08-05

New infrastructure

China's electricity market dispatch efforts to ensure peak summer electricity consumption

08-04

New infrastructure

State Grid's ultra-high voltage scale doubles

08-03

New infrastructure

Mengdian's entry into Shanghai project begins construction

08-03

New infrastructure

The world's first nuclear power to deliver ultra-high voltage has entered a critical stage

07-31

New infrastructure

11.38 million kilowatts! Shaoxing's electricity load reaches a new high

07-30

Collect
Comment
Share

Retrieve password

Get verification code
Sure