At the end of the year, the enthusiasm for domestic railway construction continued unabated, with news of multiple line renovations starting one after another. Another energy railway on the Gobi Desert in Xinjiang is about to start construction. For a long time, the Linha Railway has been the backbone channel for coal transportation from Xinjiang to the north. The single track operation mode has put continuous pressure on transportation capacity, and coal transportation is often limited. Both supply and demand sides hope that the shortcomings of the channel can be filled as soon as possible. With the progress of the construction bidding of the new Naomaohu wutong Shuishui Railway, the long troubled transport capacity problem ushers in an opportunity to solve. This 243.566km long heavy haul railway with a total investment of 11.353 billion yuan is about to open a construction picture on the Gobi Desert.

Xinjiang Coal Export Shinkansen
This line is a key project in the national medium - and long-term railway network planning, and is an important component of the northern wing layout of the Xinjiang Coal Outward Transportation One Axis, Two Wings, and Multiple Connections. It will run parallel to the double track railway from Hongliuhe to Naomaohu, jointly forming the backbone transportation channel of Linha. The line starts from Bulak Station of Jiangnao Railway and ends at wutong Water Station of Linha Railway. The construction period is 2 years. It is planned to start at the end of December and complete at the end of December 2028. The line is built according to the double line electric traction heavy load standard, with a design speed of 100 kilometers per hour and a reserved condition of 120 kilometers per hour on the plane. The traction mass can reach 10000 tons, and some sections can reach 5000 tons.

Open up transportation bottlenecks
Out of the total length of 243.566 kilometers, 80.312 kilometers of double tracks will be built, 137.393 kilometers of second tracks will be added along the Hongnao Railway, and 25.861 kilometers of second tracks will be added along the Jiangnao Railway. The project will simultaneously construct the first level three technical operation stations and locomotive turnaround sections in Naomaohu South, and also renovate the existing single track 3.74 kilometers of Linha Railway. The original single track channel had high scheduling pressure and was prone to traffic congestion. After the completion of the double track, the up and down lanes were separated, greatly improving transportation efficiency and enabling stable operation of heavy-duty trains with a capacity of 10000 tons. Keywords: Xinjiang coal transportation, Naomaohu wutong water railway, heavy haul railway

All preparations are ready
The construction drawing design of the project has been completed, and all construction funds have been secured. Capital accounts for 45%, with the remaining 55% relying on bank loans. This bidding is divided into five sections, including different construction contents such as laying and erecting strong and weak electricity in front of the station. This line takes into account the the Belt and Road construction and the western development strategy, and is different from the high-speed railway positioning of the main speed. The heavy haul coal transport line is the energy guarantee line for economic operation, and the continuous supply of Xinjiang coal will be delivered from here to stabilize the energy supply and help the steady development of the domestic economy.Editor/Li Xiaohua
Comment
Write something~