In November on the plateau, sandstorms swept through Huangzhong District, Xining City, Qinghai Province. The workshop in Ganhe Industrial Park did not stop overnight: the polycrystalline silicon production line was afraid of voltage fluctuations, and the electrolytic aluminum tank could not withstand a momentary power outage, but the curve on the central control screen moved steadily forward. Supported by the newly put into operation 330kV Jinlin indoor intelligent substation not far away. It is the first 330 kV substation put into operation by Xining Power Grid during the 15th Five Year Plan period, providing targeted services to Ganhe Industrial Park and laying a solid foundation for energy security for the park's industrial upgrading and Qinghai's clean energy industry.

The park looks forward to the arrival of new power sources
Ganhe Industrial Park gathers a large number of key electricity consuming enterprises. New energy industry chain enterprises mainly produce industrial silicon, polycrystalline silicon and other products, and have extremely high requirements for power quality; Electrolytic aluminum and deep processing enterprises require continuous and uninterrupted operation, and any interruption in power supply will directly affect production. The park is extending its supply chain towards green aluminum and new energy materials, with new projects being put into operation one after another. The demand for capacity expansion and new installation of electricity is being concentrated, and the existing power supply capacity is gradually becoming tight. Qinghai is building a national clean energy industry highland, and green electricity should not only be sent out, but also stay to drive local production lines. Jinlin Transformer has been put into operation as scheduled, timely taking on the rapidly growing demand for electricity.

The core equipment has entered the house
Jinlin Substation will build four 360000 kVA main transformers, equipped with four 330 kV outgoing lines and 16 110 kV outgoing lines. After being put into operation, the number of 330 kV outgoing lines in the area increased to 20, and the number of 110 kV outgoing lines increased to 68, further consolidating the hardware foundation of the power grid. Unlike conventional outdoor substations, it centralizes the installation of core equipment such as 330 kV and 110 kV gas insulated switchgear (GIS) indoors, effectively responding to the climate characteristics of strong sandstorms and severe winter in Qinghai and extending the service life of equipment; A complete online monitoring device can collect key operational data such as dissolved gases in the main transformer oil in real time. The equipment status has shifted from regular inspection to real-time perception, and the reliability of power supply has been synchronously improved.keywords:Engineering infrastructure

Leave a back hand for the interval between outgoing lines
Changes don't just happen within walls. State Grid Qinghai Electric Power Company carried out power load calculation during the planning stage of the park project, coordinated the planning of substation sites, outgoing line intervals and other resources, and completed power access reserve before the enterprise expanded production, so as to enable industries such as the power grid rather than industries such as the power grid. Jinlin Substation has reserved outgoing line intervals. In the future, when enterprises in the park propose capacity expansion or new electricity demand, the power supply plan will be more flexible, and the waiting time for power connection is expected to be shortened. For enterprises that rely on continuous production as their lifeline, a shorter wait gives them more confidence in stable and expanded production; For the clean energy industry in Qinghai, a more robust power base is expanding the space for upgrading.Editor/Yang Meiling
Comment
Write something~