On July 18, 2022, a reporter from Seedao.com learned from the Kunming Municipal Transportation Bureau that at present, there are 4 expressways under construction in Kunming, namely Kunming (Feder Interchange) to Yiliang Expressway, Qujing (Sanbao) to Kunming (Qingshui) Expressway (Kunming Section), Kunming-Rangdian Expressway, Changshui Airport-Shuanglong Expressway. In 2022, the construction of the above-mentioned four expressways will proceed rapidly, among which the Kunming-Rangdian Expressway is expected to be completed within the year.

According to reports, the main line of the Kundan Expressway project starts from Kunming North Third Ring Road, Xiaopuji Village, Wuhua District, Kunming City, and ends at Datuantian, northwest of Dongcun Town, Fumin County, Kunming City. If looking for a highway connection. The total length of the route is 50.2665 kilometers, with 41 bridges and 1 tunnel. Construction will start in 2019.
Up to now, 93% of the construction of the Kunming-Rangdian Expressway project has been completed, including 96% of the roadbed, 94% of the bridge, 100% of the tunnel, 52% of the housing construction, 47% of the road surface and 18% of the greening. After the project is completed and opened to traffic, it will only take about 80 minutes from Kunming via the expressway to Jiaozi Snow Mountain, which is expected to save 40 minutes of driving compared to taking the Jiaozi Snow Mountain tourist line. It is of great significance to improve the network function of the traffic trunk road in the northern part of Kunming as the connection line with the northern part of the urban circle in central Yunnan.
At present, the Kunming Municipal Bureau of Transportation is taking various measures to promote the preliminary work of "interconnection" expressway projects such as Yuxi (Yimen) to Kunming (Jinning), Wudongde to Luquan, etc., and strive to start construction as soon as possible, and continuously improve Kunming Expressway Road Network. Editor / Xu Shengpeng
Comment
Write something~