Dongfang Electric wins bid for 100MW solar thermal power generation project in Xinjiang
Seetao 2025-07-02 16:31
  • Assist in the construction of Xinjiang's new energy base and provide important support for the transition to clean energy
Reading this article requires
5 Minute

On July 1, 2025, Xinjiang Heavy Energy Power Development Co., Ltd. announced the bidding candidates for the procurement and installation of the concentrated heat collection system equipment for the 100MW solar thermal power generation project at the northern foot of the Tianshan Mountains in Xinjiang. The first bidding candidate was Dongfang Boiler Co., Ltd. of Dongfang Electric Group.

Details of bidding content

The scope of this bidding includes the procurement, installation, and commissioning of mirror field equipment and ancillary materials (including piles, peripheral columns, etc.), technical guidance for the procurement and installation of heat absorbers and ancillary equipment, procurement and installation of materials for assembly workshops, technological research and development, and 2-year maintenance services. For specific details, please refer to Appendix 2 of Volume 5 of the bidding documents for the scope of supply and services.

Project schedule arrangement

The project plans to start the construction of the mirror field and assembly workshop on July 30, 2025, complete the assembly and production of the first sun setting mirror on November 20, 2025, and complete the installation of the mirror field and enter the subsystem debugging stage on August 1, 2026.

Dongfang Boiler Co., Ltd. of Dongfang Electric Group was established in 1966 and is affiliated with China Dongfang Electric Group Co., Ltd. Since 2009, the company has been developing key equipment and technologies for solar thermal power generation, and has prioritized the development of the solar thermal industry as a strategic business focus. With strong technical strength and rich project experience, the company occupies an important position in the field of solar thermal power generation in China, and has participated in the research and supply of multiple national level scientific research and demonstration projects. (This article is from the official website www.seetao.com of Jian Dao. Reproduction without permission is prohibited, otherwise it will be prosecuted. Please indicate Jian Dao website+original link when reprinting.) Jian Dao website infrastructure engineering column editor/Yang Beihua

Comment

Related articles

New infrastructure

BalWin5 sets sail! Germany's energy transition enters the fast lane of direct current

12-13

New infrastructure

How Far sighted Intelligence Reshaps New Power Systems with AI

12-12

New infrastructure

Nanning announces AI cooperation between Guangxi and 8 ASEAN countries

12-12

New infrastructure

Huawei and ZTE secure 7.36 billion orders, Malaysia enters of 5G dual network competition

12-12

New infrastructure

Resource dilemma in data centers: Johor suspends approvals to drive industry towards

12-11

New infrastructure

China Power Engineering wins bid for Indonesia Island Power Grid Upgrade Project

12-05

Collect
Comment
Share

Retrieve password

Get verification code
Sure