The construction site of the chip city, where welding splatters, has precision equipment waiting to enter, but lacks the key power pulse. When the current of the temporary power supply first penetrated the debugging workshop, this core carrier that carries the hope of new quality productivity seized the opportunity to connect steadily to the developing energy engine before the countdown to production.
Temporary power transmission upon completion of the project
Recently, the third phase of the 10 kV transitional power supply for the chip city science and technology innovation base in Jiangbei New Area, Nanjing, was successfully powered on, seizing valuable construction time for this key integrated circuit project. The integrated circuit industry is an important strategic support for developing new quality productivity and maintaining the independent security of the industrial and supply chains. The total investment of the Chip City Science and Technology Innovation Base exceeds 19.4 billion yuan, making it the largest PPP industry project in Jiangsu Province and the core platform for the construction of the Chip City in Jiangbei New Area. At present, some of the main workshops in Phase III have been completed, and the equipment is about to enter the site for commissioning, urgently requiring power support.

Optimizing solutions to solve difficult problems
The construction time of this project is tight and the power load for debugging is high. If the traditional plan is used, several kilometers of cables need to be newly laid from a distant substation, which has a long construction period and high investment cost. State Grid Nanjing Jiangbei New Area Power Supply Company has identified the project requirements and built a temporary power supply channel based on the existing 10 kV line of the 110 kV Huqiao substation nearby, effectively shortening the construction period and saving construction investment.

The project leader Hua Cheng stated that the process from submitting the electricity demand to completing the power transmission was nearly a month ahead of schedule. The power supply department provides one-on-one exclusive services, allowing the construction party to focus on advancing the project construction. Sun Jian, Director of the Operations and Distribution Management Department of State Grid Nanjing Jiangbei New Area Power Supply Company, introduced that this transitional power supply mainly serves the 01-9 plot of the third phase of the base, with a power supply period until the end of October, fully meeting the power requirements for equipment debugging in the chip workshop. Keywords: Jiangbei New Area, Chip City, Transition Power Supply, Integrated Circuit
Upgrade the electricity business environment
State Grid Nanjing Jiangbei New Area Power Supply Company continuously improves the power business environment, creates a national level benchmark for power supply services in new areas, implements open door power connection service measures, and puts power access at the boundary of project sites, improving overall power efficiency by 20%.Editor/Gong Ziwei