On the morning of October 23, 2026, at 9:30 am, the Ulanqab Electronic Tendering and Bidding Trading Platform opened a civil engineering EPC bid worth 146 million yuan. The three bidders' quotations were squeezed to over 99.4% of the estimated price, with a difference of only 225300 yuan between the highest and lowest. Three days later, the announcement was made, and the company with the highest quotation ranked first with a score of 90.49. The winning bidder is a consortium of Beijing Telecom Planning and Design Institute and Inner Mongolia Transportation Group Xingtai Construction Engineering. This is already the third civil engineering bid they have won in the same park.

The quotation range is only 0.155%
The three bidders' quotations are 145.4656 million yuan, 145.2844 million yuan, and 145.2403 million yuan, accounting for 99.585%, 99.461%, and 99.431% of the estimated EPC price, respectively. The highest and lowest differences are 225300 yuan, with a range rate of 0.155%, and the price score on the scoring table is less than 0.1 points. A performance item or a scheme level in a technical standard can easily score 2 to 5 points. The ranking is determined in the technical score, and the technical score is determined in the performance table. There is one item in the performance table of the winning consortium that others cannot obtain: the first phase of the China Banking and Insurance Corporation's Ulanqab Data Center project, covering an area of 80000 square meters, with a design contract signed in August 2021, of the same city, type, and quantity.

Connect to the third standard within the same park
The total cost of the three civil engineering projects is 335.7538 million yuan. The winning bid for DC1 civil construction was 147.5301 million yuan, with a score of 95.09; The winning bid for DC1 civil engineering expansion is 42.7581 million yuan; The winning bid for the new construction of DC2 civil engineering is 145.4656 million yuan, with a score of 90.49. The three winning bids were led by Beijing Telecom Planning and Design Institute, with Xingtai Construction Engineering as a member. Yang Yanhong was the overall design leader for all three bids. The three winning bids span 6 months, with DC1 newly built in April, DC1 expanded in September, and DC2 newly built in October. The expansion bid will be issued 5 months after the new construction bid, and the park will roll forward. The design plan for the previous building will be finalized, and the next building will have the conditions for drawing. The same design institute is working together, so there is no need to re connect the drawings, overall layout, and pipe network interfaces. Keywords: High tech News Network, Computing Power, Intelligent Computing Center, Infrastructure

Mechatronics is the real main battlefield
The total amount of the first phase is 1.774 billion yuan, of which 336 million yuan is for civil engineering, accounting for 18.9%, and the remaining 1.438 billion yuan is for electromechanical, substation, and IT equipment. A building DC17 in Hohhot, with civil engineering of 273 million yuan and mechanical and electrical engineering of 276 million yuan, each accounting for half; Ulanqab DC2 civil engineering costs 145 million yuan, and the mechanical and electrical standards for the same level of computer room will not be lower than this amount. The same computer room building is divided into two bidding sections for basic mechanical and electrical equipment and customer support. The basic mechanical and electrical equipment pipes are for high and low voltage, diesel generator, cold source and other underlying systems, while the customer support pipes are for square cabin, end and joint debugging. The location can be selected according to capacity. The time window is in 2027, and DC1 plans to deliver the mechanical and electrical installation and commissioning in August 2027. DC2 has a construction period of 356 days and is expected to be completed by the end of 2027. In addition, the first winning candidate for the PC bid of the No. 1 110 kV transmission and transformation project is Qingdao Teruide, with a quotation of 67.898 million yuan, which is less than half of the main civil engineering. The qualification threshold and performance requirements are a different set, which is more cost-effective for enterprises that want to enter the park for the first time.Editor/Gao Xue