Major domestic projects

Railway engineering

1. China Railway Tunnel Bureau, contracted the SJSG-2 bid section with a total price of 1.99721 billion yuan and a construction period of 2009 calendar days for the construction of the Zhujiangkou tunnel section of the new Shenzhen to Jiangmen railway.

2. China Railway First Bureau, China Railway Third Bureau and other parties have contracted S1 bid section for the construction of the newly-built Aksu-Alar railway project at a total price of 86786 million yuan and a construction period of 24 months.

3. China Railway Construction Engineering, newly built 5 station buildings along the Hubei section of Zhengzhou-Wanzhou Railway, production and living houses and related projects, customer service information system integration and related projects; newly-built Anqing-Jiujiang Railway Huangmei South Station and other projects ZWHBZF-3 standard construction general The price contract is 521.15 million yuan, and the construction period is 448 calendar days.

Road construction

4. China Railway Tunnel Bureau, National Highway 310 Jianzha to Gonghe Highway Project JGSG-1 section of the Yashiga-Ashigong section project, 1.67298 billion yuan, and a construction period of 1461 calendar days.

5. China Railway Fourth Bureau, Yancheng District Fan Highway South Section (Phase II) construction project, 816.07 billion yuan, construction period of 24 months.

6. China Railway Seventh Bureau, China Railway Construction Engineering, the second batch of civil engineering construction SG02 contract section of the first phase project of Guangzhou Conghua to Huangpu Expressway, 814.76 million yuan, construction period -.

7. China Railway Construction Engineering and other parties, the general contracting project for the design and construction of the Huibu-Hejia Highway in Changshan County, Quzhou City, with a construction period of 30 months.

Municipal and other projects

8. China Railway Tunnel Bureau and other parties, Dengwang District (Plot C), Nanguan Beigu District and Tucheng District, Liaocheng City Dongchangfu District shantytown renovation project EPC project, 3.7079.2 billion yuan, 720 calendar days day.

9. China Railway Construction Engineering, China Railway First Bureau and other parties, Beijing City Sub-Central Station Comprehensive Transportation Hub Project 02 bid section, 3.29417 billion yuan, the construction period is 1553 calendar days.

10. China Railway Second Bureau, China Railway Tunnel Bureau, Hangzhou Airport Rail Express Project Warehouse Front Vehicle Base Ⅱ and Ⅳ standard, 1.81172 billion yuan, construction period 486 calendar days -494 calendar days.

11. China Railway Construction Engineering, Lunan·Jinyujiayuan Engineering General Contracting (EPC) project, 1.457.8 billion yuan, construction period of 730 calendar days

12. China Railway, China Railway First Bureau, China Railway Wuhan Electric Chemical Bureau, the first phase of Guangzhou Rail Transit Line 7, the electrical and mechanical engineering of the Shunde section of the west extension project, 1.20981 billion yuan, construction period -.

13. China Railway Third Bureau, the construction bid section of Sibao parking lot for the first phase of Hangzhou Metro Line 9, 1.14251 billion yuan, construction period of 560 calendar days

14. China Railway Tenth Bureau and other parties, Zibo Open Industrial Processing Center 4# plot workshop (J17#-J20#) project, 1.11651 billion yuan, construction period of 407 calendar days.

15. China Railway Tunnel Bureau, Sichuan Dujiangyan to Siguniangshan Mountain Rail Transit Poverty Alleviation Project Station Civil Engineering 1 bid (DSZQ-1 bid), 1.0452.5 billion yuan, construction period 1,826 calendar days.

16. China Railway Second Bureau, Suzhou Rail Transit Line 7 (Second Batch), Line 8 (Fourth Batch) Civil Engineering Construction Project VII-TS-05 Standard, 97835 million yuan, 1448 calendar days.

17. China Railway Fourth Bureau, Xuzhou Sanhuan South Road rapid transformation project construction general contracting SHNL-SG-4 bid section, 96364 million yuan, construction period of 18 months.

18. China Railway Second Bureau, Urumqi Hengda Jiujiawan Project, the first phase of the main body and surrounding supporting projects, the second, third, and fourth bid sections, 917 million yuan, construction period -.

19. China Railway Fifth Bureau, Pingdingshan City Exhibition Center project and supporting housing and underground garage project (Phase I of Sun City), 830.09 million yuan, construction period of 731 calendar days.

20. China Railway Tenth Bureau, Zibo Station Passenger Transport Facilities Reconstruction Project ZBZG-1 bid section construction total price contracted, 78612 million yuan, 36 months

21. China Railway Electrification Bureau and other parties, the general contracting of the project of the Yaozhuang area development project (including the road network on the west side of the Zhaobing River) in the Yaozhuang 3# plot in the airport noise zone (demolition resettlement housing), 6.9936 100 million yuan, the construction period is 900 calendar days.

22. China Railway Fifth Bureau, Guiyang Hengda Cultural Tourism City 13#, 15# group main body and supporting construction project, 655 million yuan, construction period 558 calendar days.

23. China Railway Fifth Bureau and other parties, Shenzhen Airport Plot DU09-69 Talent Housing Project Design, Procurement and Construction General Contracting Project (EPC), 649.72 million yuan, construction period of 858 calendar days.

24. China Railway Tunnel Bureau, municipal engineering of Buji Sanlian Road, Longgang District, Shenzhen, 624.54 million yuan, construction period of 474 calendar days.

25. China Railway Fourth Bureau, S304 Yuhang Xiaolin to Tangqi Section Reconstruction and Expansion Project Construction Section SG02, 608.8 million yuan, construction period of 24 months.

26. China Railway Eighth Bureau and other parties, EPC (general contracting of design, survey and construction) for the comprehensive construction project of the funeral home in Wanshan District, Tongren City, 540.06 million yuan, with a construction period of 24 months.

Major overseas projects

1. China Railway Construction Engineering, Tanzania Dodoma High Court project, 129,740.29 million Tanzanian shillings, equivalent to RMB 40228 million, construction period of 30 months.

The total bid price of the above-mentioned projects was approximately RMB 30.699.2 billion, accounting for approximately 3.62% of the company's operating income in 2019 under the Chinese Accounting Standards. Editor/Peng Xue

Comment

Related articles

Special

Xiopm SPACE quantitative hyperspectral intelligent computing satellite officially launched

05-15

Special

The Chinese quantum computer "Chapter Nine No. 4" has been launched

05-14

Special

China's mineral exploration breakthrough discovers 13 billion ton oil fields

04-30

Special

Digging deeper into the ground and breaking through to the high-end market

04-28

Special

Milestone progress! The world's first, successfully ignited

04-27

Special

CANGYU SPACE was invited to give a keynote speech at CSC2026

04-24

Collect
Comment
Share

Retrieve password

Get verification code
Sure