Daguang Expressway Ji'an to Nankang Housing Construction Project Bidding
Seetao 2022-07-15 14:39
  • This project is divided into 1 category, namely housing construction, and is divided into 3 bidding sections
  • The planned start time of this project is September 2022, and the project construction period is 22 months
Reading this article requires
8 Minute

On July 14, 2022, the Jiangxi Provincial Department of Transportation issued a tender announcement for the construction of the housing construction project of the reconstruction and expansion project of the G45 Daguang Expressway from Ji'an to Nankang. The management company, the project approved the estimated budget of 16.69 billion yuan.

Project Overview

The reconstruction and expansion project of the Ji’an-Nankang section of G45 Daguang Expressway starts from the direction of Wuning, north of Ji’an South Hub, Jizhou District, Ji’an City. The starting point is K2872+500. The intercommunication location of the Shibatang hub in Nankang District, Ganzhou City, is connected to the starting point of the expansion project of the Nankang-Longnan section of the G45 Daqing-Guangzhou Expressway. The route passes through Jizhou District of Ji'an City, Ji'an County, Taihe County, Wan'an County, Suichuan County and Nankang District of Ganzhou City. The total length of the route is 145.4 kilometers.

8 new toll stations along the project line, namely Ji'an County Toll Station, Taihe West Toll Station, Taihe South Toll Station, Shaokou Toll Station, Wan'an Toll Station, Suichuan Toll Station, Tangcun Toll Station, Hengshi Toll Station, 6 Maintenance and renovation of 1 toll station, namely Lao Ji'an County Toll Station, Lao Wan'an Toll Station, Lao Suichuan Toll Station, Lao Tang Village Toll Station, Lao Heng City Toll Station, Lao Jin Stone Maintenance Station, 2 Parking Areas Taihe Parking Area, Nan Kang parking area, 1 maintenance station towel stone maintenance station, 1 monitoring and communication sub-center Changtai monitoring and communication sub-center.

technical standard

The entire line of the project adopts the two-way eight-lane expressway standard with a design speed of 100 km/h; the main body adopts the expansion method of widening on both sides, and the method of single-side widening or near-end separation is adopted in the difficult terrain. The width of the double-sided widened roadbed is 41 meters, the width of the one-sided widened roadbed is 47 meters, and the width of the newly-built roadbed is 20.5 meters. The pavement structure is asphalt concrete pavement; the vehicle load is highway-I grade; the design flood frequency of bridges, culverts and roadbeds are 1/100; the navigation grades are VI, VII and VIII; , monitoring, communication, charging, power supply, lighting and services and other traffic engineering and facilities along the line.

Division of bids: This tender is divided into 1 category and a total of 3 bids, namely: Category I, housing construction, 3 bids, FJ1 bid, FJ2 bid, and FJ3 bid.

Planned construction period: The project construction period is 22 months, the defect liability period is 24 months, and the warranty period is 60 months. The project is scheduled to start construction in September 2022. Keywords: engineering news, engineering construction, engineering construction information

Acquisition and submission of tender documents

Those who intend to participate in the bidding, please log in to Jiangxi Provincial Public Resources Trading Network using CA digital certificate through the Internet from 00:00 on July 15, 2022 to 00:00 on July 20, 2022, and obtain the bidding documents in the trading system and related information. The deadline for submission of tender documents is 09:30 on August 16, 2022.Editor/Zhao E

Comment

Related articles

Transportation

Montenegro's € 18 million road construction begins

05-13

Transportation

The South Xinjiang Railway Capacity Expansion Project has achieved phased results

05-13

Transportation

The head of Gansu Public Transport Construction Group went to Jinchang for exchange

05-12

Transportation

Suinei section officially enters the stage of construction drawing review

05-12

Transportation

37.7 billion yuan Xinjiang Yining Aksu Railway Project launches bidding

05-12

Transportation

Over 10 billion yuan! Another highway has made significant progress in construction

05-11

Collect
Comment
Share

Retrieve password

Get verification code
Sure