Wind power
Longyuan Sheyang 1 million-kilowatt offshore wind power project
Seetao 2022-12-20 14:44
  • The project is scheduled to start on February 1, 2023, with a total installed capacity of 1,000MW
  • At present, China's offshore wind power installed capacity has surpassed that of the United Kingdom, becoming the world's largest offshore wind power market
Reading this article requires
4 Minute

The eastern coastal provinces are actively promoting the development of offshore wind power, and offshore wind power is moving forward at a high speed! Recently, Huadian Heavy Industries Co., Ltd. and China Power Construction Group East China Survey and Design Institute Co., Ltd. signed the "Contract for the First Bid Section of Fan Foundation Manufacturing, Construction and Fan Hoisting of Guoneng Longyuan Sheyang 1,000,000-kilowatt Offshore Wind Power Project". The amount is approximately RMB 1,406,001,624.55 (tax included).

Performance period: planned start date: February 1, 2023; planned completion date: October 31, 2023; total calendar days of the construction period: 273. If the total number of calendar days of the construction period is inconsistent with the number of days of the construction period calculated based on the aforementioned planned start and completion dates, the total number of calendar days of the construction period shall prevail.

The wind farm is located in the southeast sea area of the Sheyang Estuary, at the northernmost point of the radiating sandbar. The center of the site is about 65km offshore, with a total installed capacity of 1,000MW. Two 220kV offshore booster stations and a 220kV onshore centralized control center are newly built in this wind farm. The generated energy is collected to the 35kV busbar of the offshore booster station, boosted to 220kV by the main transformer, and passed through 4 circuits of 220kV submarine cables (three-core 630mm2) to the landing point, after landing, it is connected to the 220kV onshore centralized control center of the wind farm, and then connected to the system station. Editor/Xu Shengpeng


Comment

Related articles

Wind power

Brazil added 703.7 MW of installed capacity in October, with wind power accounting for 90%

11-10

Wind power

Shaanxi Yan'an Ansai Wind Power Project Full Capacity Grid connected Power Generation

11-09

Wind power

The First Tower of the GEPIC Minqin Wind‑Solar Project Is Erected

11-09

Wind power

China's Energy Map Reaches 4,000 Meters Up

11-07

Wind power

Green Electricity Powers Border Duties Across Alashankou Port

11-05

Wind power

Southeast Asian sea breeze brings green power, fueling new momentum for the Silk Road

11-01

Collect
Comment
Share

Retrieve password

Get verification code
Sure