The installation of T-beam for Bridge 8 of Tajikistan ON2 project has been completed
Seetao 2024-07-16 08:59
  • This project deepens the cooperation between China and Tajikistan in the field of infrastructure construction
Reading this article requires
5 Minute

On July 10th, with the installation of the last T-beam in place, all 49 24 meter T-beams of the 8th bridge of Zhejiang Jiaotong Tajikistan ON2 project under Zhejiang Jiaotong Group were erected, marking the completion of the project's beam and slab erection work.

The No. 8 bridge constructed this time is a simply supported beam bridge, with a total length of 169.49 meters and a T-beam length of 24 meters per span, totaling 7 spans. The single beam weighs about 40 tons, and the pier columns are as high as 22 meters, making it the tallest and longest bridge in the project. Due to the bridge standing on the valley, the river water rises sharply during rainfall, and temporary bridges often face the risk of being washed away. Additionally, the river channel is not navigable, posing great challenges to construction. Therefore, Bridge No. 8 has become one of the important engineering nodes of this project.

In order to solve construction problems and reduce construction costs, the project department conducted multiple on-site inspections and in-depth research, fully explored and utilized local resources, and ultimately decided to adopt the bridge erecting machine scheme for beam erection. In addition, the project department boldly innovated by transforming the flatbed locomotive into two dedicated beam transport vehicles, effectively solving the difficulty of beam transport and achieving the goal of improving transportation efficiency and construction efficiency, greatly shortening the construction period. Keywords: overseas engineering, international engineering construction, foreign engineering construction news.

The successful installation of the T-beam on Bridge 8 marks a new breakthrough in project construction, enhancing the confidence of all participants and accelerating the pace of construction. Next, the Tajikistan ON2 project will accelerate the construction of bridge deck paving and ancillary facilities to ensure the successful completion of the opening target. (This article is from the official website of Jian Dao: www.seetao.com. Reproduction without permission is prohibited, otherwise it will be prosecuted. Please indicate Jian Dao website+original link when reprinting.) Jian Dao website mechanical column editor/Zhou Yingwen

Comment

Related articles

Municipal

G228 Dandong Line Nangu Section Repair and Maintenance Project Commences

10-16

Municipal

EPCC General Contract for 300000 Tons Propane Dehydrogenation to Polypropylene Project

09-25

Municipal

Pakistan's white oil pipeline construction is about to start

09-20

Municipal

Kazakhstan's manufacturing industry surpasses mining industry for the first time

09-12

Municipal

Nanchang AMEC GaAs-based LED MOCVD equipment project was signed

09-11

Municipal

From northern Shaanxi to Guanzhong, the 750 kV channel started

09-02

Collect
Comment
Share

Retrieve password

Get verification code
Sure