Construction of the upper part of the China Mongolia cross-border railway
Seetao 2026-07-14 14:42
  • Cross border railway platform between China and Mongolia ends, promoting cooperation between the two countries
Reading this article requires
7 Minute

On July 12, 2026, with the completion of the final concrete pouring, the construction of all 324 bearing platforms for the China Mongolia Cross border Railway Project has been completed. From the desert and Gobi to the depths of the grasslands, each pedestal is like a solid foundation, firmly rooted on the land of the China Mongolia border. The completion of this milestone marks the official transition of the second cross-border railway connecting the two countries into the upper structure construction stage, including pier body pouring and prefabricated beam erection, taking a crucial step towards the early completion and opening of the entire line.

Labor competition drives efficient promotion

To efficiently promote the construction of the bearing platform, the project takes the six to six innovation labor competition as the starting point, dynamically optimizes the construction plan and on-site resource allocation, refines monthly construction tasks, and fully guarantees the steady progress of the project construction. The project team decomposed and implemented the construction tasks of 324 abutments layer by layer, ensuring that each abutment was completed with high quality according to the plan through continuous progress tracking and dynamic adjustment, and buying valuable time for the subsequent upper structure construction.

Night pouring solves the problem of strong winds

In response to the construction difficulties of frequent strong winds and dust in the local area, which can easily affect the quality of concrete forming, the project team optimized the construction process based on the actual situation on site, and prioritized the pouring of concrete during the windless period at night, effectively avoiding quality defects such as component roughness and missing reinforcement. At the same time, we will closely monitor the entire chain of concrete mixing, transportation, pouring, vibration, and curing, establish a quality control system throughout the entire process, ensure that each pier construction is organized in an orderly manner and of reliable quality, and lay a solid foundation for the safety of bridge structures. Keywords: the Belt and Road news, China Mongolia railway infrastructure, cross-border railway

Injecting New Momentum into Energy Economy and Trade

As the second cross-border railway between China and Mongolia, the project will connect the Ganquan Railway and Mongolia's southbound railway after completion, which will further promote the interconnection of energy resources, infrastructure, and economic and trade exchanges between the two countries, and drive the upgrading of cross-border logistics, industrial parks, border trade services and other industries between China and Mongolia. The opening of this railway channel is of great significance for promoting China Mongolia economic cooperation and jointly building the the Belt and Road with high quality, and will also bring tangible development opportunities for the two peoples.Editor/Gao Xue

Comment

Related articles

Construction Frontline

Etihad Railway Test Run

07-11

Construction Frontline

Kenya's $5.4 billion SGR West Extension Project fully begins construction

07-10

Construction Frontline

Uzbekistan signs $2.5 billion new airport contract and lands

07-09

Construction Frontline

4.2 billion! New line added to Northeast energy artery

07-08

Construction Frontline

TBEA Completes Power Projects in Timor-Leste to Boost Local Infrastructure

07-08

Construction Frontline

CASCO collaborates with Dubai to build a joint rail transit laboratory

07-07

Collect
Comment
Share

Retrieve password

Get verification code
Sure