Kazakhstan power grid heating network synchronous update
Seetao 2026-07-29 09:16
  • 84 billion tenge of funding is in place, with 9 units, 55 boilers, and 51 turbines included in the annual overhaul list
Reading this article requires
5 Minute

Kazakhstan at the end of July is less than two months away from the heating season. The five power plants in Semey, Uralsk, Taraz, Aktau, and Temytau are still in the red risk zone, and equipment aging is an urgent issue. In 2026, the government will allocate 384 billion tenge for nationwide power plant maintenance, an increase of 9% compared to last year. The funds will come from electricity price adjustments, and each power station will identify weak links and prioritize repairs.

Hidden defects slow down progress

According to the plan, major repairs for 9 generator sets, 55 boilers, and 51 turbines need to be completed by 2026. As of now, 2 units have been completed and 2 more are under maintenance; 13 boilers have been repaired, while 27 are still under construction; 8 turbines have been delivered, and 16 are still in progress.

The maintenance work is strictly carried out according to the plan, but some facilities have exposed hidden defects, which has increased the workload. In addition, over 500 auxiliary equipment units across the country have been included in the maintenance scope simultaneously. According to the plan, the northern and eastern regions must complete the preparation of the heating network before September 1st, and the main maintenance of the power station must be completed before September 15th; The southern and western regions will be postponed until the end of September. Keywords: power plant maintenance, Central Asian news

Target to reduce aging rate to 52%

Synchronized promotion of power grid renovation - approximately 6300 kilometers of transmission lines, 135 substations, and 1253 distribution points have been repaired, with plans to update over 17000 kilometers of lines and 3400 distribution points by the end of the year. In terms of heating network, 65 kilometers have been completed, and another 278 kilometers are under construction. The average aging rate of power station equipment is planned to be reduced to 52% by the end of the year. Five high-risk power plants are still in the red zone, and hidden dangers have not been eradicated.Editor/Cheng Liting

Comment

Related articles

Central Asia

Chinese enterprises invest 550 million US dollars in Uzbekistan

07-29

Central Asia

KTZ Unveils Triple Listing Plan for Cross-border Financing Upgrade

07-29

Central Asia

Kazakhstan-Uzbekistan Forum Boosts Oilseed Sector, Kazakhstan Leads Central Asian Market

07-28

Central Asia

CREC Electrification, Pakistan Marine Ministry Align on Corridor Infrastructure Upgrades

07-26

Central Asia

New Digital Engine in Central Asia: Accelerating Digital Construction in Uzbekistan

07-24

Central Asia

Chinese fuel arrives in Kyrgyzstan for the first time, resolving the 'fuel shortage'

07-24

Collect
Comment
Share

Retrieve password

Get verification code
Sure