Service-Free Beam Replacement Revitalizes Century-Old Railway Bridge
Seetao 2026-08-24 11:11
  • Beam Replacement Completed Without Service Suspension, Revitalizing Century-Old Beijing-Shanghai Railway Bridge
Reading this article requires
6 Minute

As the core transportation artery in China, the Beijing Shanghai Railway has dense traffic and heavy freight tasks, and the renovation of old bridges has always been a challenge for the industry. On August 20, 2026, CR14G innovated the construction method and completed the overall replacement of a century old bridge without affecting train traffic, solving the pain points of mainline renovation.

Facing construction challenges head-on

The reconstruction bridge of the Zaozhuang section of the Beijing Shanghai Railway was first built in 1911 and has been in service for over a hundred years, but there are certain safety hazards. This route operates over 200 trains per day and accounts for nearly one-fifth of the country's annual freight volume, making it a crucial transportation channel. The biggest difficulty of this renovation is that the entire process cannot be stopped, trains need to pass normally, and conventional track breaking construction methods are completely unsuitable, which puts extremely high demands on construction technology and overall planning ability.

Innovative construction technology

The project team innovatively adopts a relay beam replacement process, first setting up a temporary structure to bear the train load, reducing the burden of dismantling the old beam, synchronously pouring the new bridge on site, and smoothly completing the line handover. To minimize operational impact, the project will complete more than 90% of its processes off-site ahead of schedule, and only utilize the absence of trains at night to carry out core operations. Equipped with a dual security system on site, real-time warning of trains, monitoring of bridge pier deformation, and comprehensive protection of construction safety. Keywords: non-stop beam replacement, railway renovation

Empower road network upgrade

This century old bridge replacement completely eliminates safety hazards of old bridges, not only meeting the needs of local road traffic, but also laying a solid foundation for railway speed increase. The successful practice of non-stop renovation has overcome the problem of retrofitting over aged bridges on main lines, formed a mature and replicable construction mode, provided high-quality demonstration models for the upgrading of busy railway trunk lines nationwide, and helped improve the quality and efficiency of the national railway network.Editor/Min Jing

Comment

Related articles

Transportation

EU Backs Bangladesh’s First Railway Electrification Project

08-21

Transportation

Argentine Delegation Explores Mexico City Transit, Promotes CRRC Cooperation

08-21

Transportation

Speed up construction of Kasa South Station

08-21

Transportation

Chinese Consortium Secures Vietnam Railway Consulting Project

08-21

Transportation

G0616 Wuhai section connects the north and south ports of Bayannur

08-20

Transportation

$500‑Million Light Rail Project Planned in Brazil for Rail Transit Cooperation

08-19

Collect
Comment
Share

Retrieve password

Get verification code
Sure